7421 N CORBIN AVE 91306
Certificate Information: 7421 N CORBIN AVE 91306
- Application / Permit
- 25010-20000-01368
- Plan Check / Job No.
- B25VN08816
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3
- Permit Issued
- Issued on 4/25/2025
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/8/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/19/2025 | MOHAMMAD ESMAILI |
| Issued | 4/25/2025 | APPLICANT |
| CofO in Progress | 9/9/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/23/2026 | JOHN JANSON |
| CofO Issued | 2/23/2026 | JOHN JANSON |
| Permit Finaled | 2/23/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2025 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 4/12/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 4/18/2025 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/1/2025 | No Access for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 5/20/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 5/20/2025 | Approved | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 5/28/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/13/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 6/13/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 6/17/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/14/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 7/14/2025 | Approved | ALEXANDER HANDY |
| Insulation | 7/14/2025 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/14/2025 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 7/18/2025 | Approved | ALEXANDER HANDY |
| Insulation | 7/18/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/18/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 7/18/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 8/15/2025 | Partial Approval | SCOTT SOBEL |
| Underground Mechanical | 8/19/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Underground Mechanical | 8/21/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 9/5/2025 | Approved | KRISTEN CAUSEY |
| Final | 9/5/2025 | Corrections Issued | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 9/5/2025 | Approved | KRISTEN CAUSEY |
| Green Building Final | 9/5/2025 | Approved | KRISTEN CAUSEY |
| HVAC-Final | 9/5/2025 | Approved | KRISTEN CAUSEY |
| PLUMBING-Final | 9/5/2025 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | KRISTEN CAUSEY |
| Service/Power Release | 9/5/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Smoke Detectors | 9/5/2025 | Approved | KRISTEN CAUSEY |
| Final | 9/8/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 9/8/2025 | Approved | ALEXANDER HANDY |