14004 W SYLVAN ST 91401

Certificate Information: 14004 W SYLVAN ST 91401

Application / Permit
25010-20000-01351
Plan Check / Job No.
B25VN08648
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY SINGLE FAMILY DWELLING UNIT WITH ATTACHED PORCHED AND STORAGE (EXTERIOR ACCESS ONLY) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 6/25/2025
Issuing Office
Valley
Current Status
Issued on 6/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/1/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 4/3/2025 BENNY WONG
Corrections Issued 4/5/2025 ALFRED RAMIREZ
Quality Review Completed 4/8/2025 STEVEN KIM
Building Plans Picked Up 4/10/2025 APPLICANT
Plan Check Approved 5/16/2025 ALFRED RAMIREZ
Issued 6/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/15/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/18/2025 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 4/18/2025 ERNEST TSE
Sewer availability Cleared 4/18/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 4/22/2025 KURT CORRAL
CPC Cleared 4/28/2025 JASON CHAN
Roof/Waste drainage to street Cleared 4/29/2025 BIAINA HARITUNIAN
Zoning Plan Check Cleared 5/6/2025 BENNY WONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/25/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/25/2025 Corrections Issued NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 7/29/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 7/29/2025 Partial Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 8/7/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 10/23/2025 Partial Approval RYAN SALAZAR
Sewer 10/23/2025 Approved RYAN SALAZAR
Special/Order Compliance 10/23/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 12/17/2025 Approved RYAN SALAZAR
HVAC-Rough 12/17/2025 Approved RYAN SALAZAR
PLUMBING-Rough 12/17/2025 Partial Approval RYAN SALAZAR
Rough-Elec/Plmb/HVAC 12/17/2025 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 1/8/2026 Approved RYAN SALAZAR
Green Building Rough 1/8/2026 Approved RYAN SALAZAR
PLUMBING-Rough 1/8/2026 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 1/8/2026 Approved RYAN SALAZAR
Insulation 2/4/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/4/2026 Partial Approval VINCENT HANLEY
Drywall Nailing 2/10/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/10/2026 Partial Approval VINCENT HANLEY
Shower Pan 2/23/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/5/2026 Approved VINCENT HANLEY