18771 W MAPLEWOOD LANE 91326
Certificate Information: 18771 W MAPLEWOOD LANE 91326
- Application / Permit
- 25010-20000-01338
- Plan Check / Job No.
- B25VN08632
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED TRELLIS PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/8/2025
- Issuing Office
- Current Status
- CofO in Progress on 7/7/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2025 | KAMYAR EMAMI |
| Corrections Issued | 4/30/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 5/29/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/18/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 6/25/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/8/2025 | GIOVANNY CHAVEZ |
| Issued | 7/8/2025 | APPLICANT |
| CofO in Progress | 7/7/2026 | JACK KARGODORIAN |
Permit Application Clearance Information
| ZA Case | Cleared | 5/2/2025 | JASON CHAN |
| ZA Case | Cleared | 5/2/2025 | JASON CHAN |
| ZA Case | Cleared | 5/2/2025 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 5/6/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | COLIN LOREDO |
Contact Information
| Contractor | Lionelli Masonry Inc; Lic. No.: 367772-B | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 8/1/2025 | Approved | DAVID SCANTLIN |
| Wood Frame | 3/17/2026 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/26/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/26/2026 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/29/2026 | Approved | JACK KARGODORIAN |
| Final | 6/29/2026 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 6/29/2026 | Approved | JACK KARGODORIAN |
| Green Building Rough | 6/29/2026 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/29/2026 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 6/29/2026 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 6/29/2026 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 6/29/2026 | Approved | JACK KARGODORIAN |