13747 W CALVERT ST 91401
Certificate Information: 13747 W CALVERT ST 91401
- Application / Permit
- 25010-20000-01297
- Plan Check / Job No.
- B25VN08317
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONSTRUCT NEW DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(2)
- Permit Issued
- Issued on 7/25/2025
- Issuing Office
- Current Status
- Issued on 7/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/10/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/21/2025 | KAMYAR EMAMI |
| Issued | 7/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/16/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Quantum Construction & Design; Lic. No.: 1061867-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/11/2025 | Partial Approval | RYAN SALAZAR |
| Piling/Pier/Caisson | 8/15/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/19/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/7/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 10/7/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 10/7/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/14/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/14/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/14/2025 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 10/28/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/15/2026 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/15/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/15/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/15/2026 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 1/15/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/15/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 1/21/2026 | Approved | RYAN SALAZAR |
| Insulation | 1/26/2026 | Not Ready for Inspection | DAVID MATSON |
| Drywall Nailing | 1/28/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/12/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 3/12/2026 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/27/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Sewer | 4/29/2026 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/29/2026 | Approved | VINCENT HANLEY |