1259-1259 1/2 E ADAMS BLVD 90011

Certificate Information: 1259-1259 1/2 E ADAMS BLVD 90011

Application / Permit
25010-20000-01259
Plan Check / Job No.
B25VN07987
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN NEW 25' X 96' 2-STORY DUPLEX W/ 2-CAR GARAGE AT REAR AND 1-CAR GARAGE IN FRONT. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
CofO Issued on 3/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 RAPHAEL ROSAS
Assigned to Zoning Architect 3/27/2025 ELAHE MERRIKHI
Corrections Issued 4/1/2025 RAPHAEL ROSAS
Quality Review Completed 4/2/2025 STEVEN KIM
Applicant returned to address corrections 10/15/2025 RAPHAEL ROSAS
Plan Check Approved 11/4/2025 RAPHAEL ROSAS
Issued 11/17/2025 APPLICANT
CofO in Progress 3/26/2026 ALEJANDRO DE ARTOLA
Permit Finaled 3/30/2026 DEROLD HAUFF
CofO Issued 3/30/2026 DEROLD HAUFF
Permit Finaled 3/30/2026 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 4/8/2025 YINGSHI HUANG
CPC Cleared 4/8/2025 YINGSHI HUANG
Hydrant and Access approval Cleared 4/16/2025 LAVEON RIDER
Low Impact Development (LID) Cleared 4/18/2025 ERNEST TSE
Address approval Cleared 4/22/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 4/22/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/24/2025 DAVID LOPEZ
Sewer availability Cleared 4/24/2025 DAVID LOPEZ
Frnt yard landscape/Water mgmt Cleared 4/30/2025 YINGSHI HUANG
Highway dedication Cleared 7/23/2025 TREVOR QUAN
Permit Cleared 7/23/2025 TREVOR QUAN
SB8 RUD Cleared 9/22/2025 KENNETH LE
Tenant Habitability Plan Cleared 9/22/2025 HUGO GARRIDO GARZA
Zoning Plan Check Cleared 10/24/2025 ELAHE MERRIKHI

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/8/2025 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 12/15/2025 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 12/15/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Approved ALEJANDRO DE ARTOLA
Insulation 12/16/2025 Approved ALEJANDRO DE ARTOLA
Sewer 12/16/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/28/2026 Approved ALEJANDRO DE ARTOLA
Gas Test 1/28/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/28/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/29/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 1/29/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 1/29/2026 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/29/2026 Approved ALEJANDRO DE ARTOLA
Insulation 2/2/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/2/2026 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 2/3/2026 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 2/10/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/10/2026 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/19/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/19/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/20/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/20/2026 Approved ALEJANDRO DE ARTOLA
Final 3/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/20/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 3/20/2026 Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/20/2026 Approved ALEJANDRO DE ARTOLA
Final 3/23/2026 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 3/23/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/23/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/24/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/24/2026 Approved ALEJANDRO DE ARTOLA
Final 3/25/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 3/25/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/25/2026 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 3/25/2026 Approved ALEJANDRO DE ARTOLA
Final 3/26/2026 OK to Issue CofO ALEJANDRO DE ARTOLA