1259-1259 1/2 E ADAMS BLVD 90011
Certificate Information: 1259-1259 1/2 E ADAMS BLVD 90011
- Application / Permit
- 25010-20000-01259
- Plan Check / Job No.
- B25VN07987
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN NEW 25' X 96' 2-STORY DUPLEX W/ 2-CAR GARAGE AT REAR AND 1-CAR GARAGE IN FRONT. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/17/2025
- Issuing Office
- Current Status
- CofO Issued on 3/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 3/27/2025 | ELAHE MERRIKHI |
| Corrections Issued | 4/1/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 4/2/2025 | STEVEN KIM |
| Applicant returned to address corrections | 10/15/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 11/4/2025 | RAPHAEL ROSAS |
| Issued | 11/17/2025 | APPLICANT |
| CofO in Progress | 3/26/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/30/2026 | DEROLD HAUFF |
| CofO Issued | 3/30/2026 | DEROLD HAUFF |
| Permit Finaled | 3/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/8/2025 | YINGSHI HUANG |
| CPC | Cleared | 4/8/2025 | YINGSHI HUANG |
| Hydrant and Access approval | Cleared | 4/16/2025 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 4/18/2025 | ERNEST TSE |
| Address approval | Cleared | 4/22/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/22/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/24/2025 | DAVID LOPEZ |
| Frnt yard landscape/Water mgmt | Cleared | 4/30/2025 | YINGSHI HUANG |
| Highway dedication | Cleared | 7/23/2025 | TREVOR QUAN |
| Permit | Cleared | 7/23/2025 | TREVOR QUAN |
| SB8 RUD | Cleared | 9/22/2025 | KENNETH LE |
| Tenant Habitability Plan | Cleared | 9/22/2025 | HUGO GARRIDO GARZA |
| Zoning Plan Check | Cleared | 10/24/2025 | ELAHE MERRIKHI |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2025 | Conditional Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/15/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 12/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/28/2026 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 1/28/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/28/2026 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/29/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/29/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/29/2026 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 1/29/2026 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 2/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/2/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/10/2026 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/10/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/19/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/19/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/23/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 3/23/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/23/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/24/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/24/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/25/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/26/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |