6907 N NOBLE AVE 91405

Certificate Information: 6907 N NOBLE AVE 91405

Application / Permit
25010-20000-01238
Plan Check / Job No.
B25VN07830
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER GCS 66323(a)(2)
Permit Issued
Issued on 9/9/2025
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/26/2025 GURUNATH NESARAJAH
Corrections Issued 3/27/2025 GURUNATH NESARAJAH
Plan Check Approved 7/23/2025 LUISANGEL VALENZUELA
No Progress 9/8/2025 LUISANGEL VALENZUELA
Plan Check Approved 9/8/2025 LUISANGEL VALENZUELA
Issued 9/9/2025 APPLICANT
CofO in Progress 3/20/2026 VINCENT HANLEY
Permit Finaled 5/19/2026 RUBEN SALAS
Permit Finaled 5/19/2026 RUBEN SALAS
CofO Issued 5/19/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 5/21/2025 GEVORK KARAPETYAN
Construction within easement Cleared 5/21/2025 GEVORK KARAPETYAN
Address approval Cleared 6/18/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 6/18/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/18/2025 MICHAEL BROWN
Sewer availability Cleared 6/18/2025 MICHAEL BROWN

Contact Information

Contractor Arg General Contractors; Lic. No.: 1081051-B       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2025 Corrections Issued RYAN SALAZAR
Special/Order Compliance 9/30/2025 Corrections Issued RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 10/3/2025 Corrections Issued RYAN SALAZAR
Sewer 10/3/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/10/2025 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Approved RYAN SALAZAR
HVAC-Rough 11/14/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/14/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 11/14/2025 Approved RYAN SALAZAR
Insulation 11/20/2025 Corrections Issued JACK KARGODORIAN
Shower Pan 12/10/2025 Approved MICHAEL CORTEZ
Drywall Nailing 12/16/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/16/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 1/26/2026 Approved JAVIER RAMOS JR
Final 1/26/2026 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 1/26/2026 Approved JAVIER RAMOS JR
Green Building Final 1/26/2026 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 1/26/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 1/26/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 1/26/2026 Corrections Issued JAVIER RAMOS JR
Smoke Detectors 1/26/2026 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/19/2026 Approved VINCENT HANLEY
Final 3/19/2026 OK to Issue CofO VINCENT HANLEY
Green Building Final 3/19/2026 Approved VINCENT HANLEY
Green Building Rough 3/19/2026 Approved VINCENT HANLEY
HVAC-Final 3/19/2026 Approved VINCENT HANLEY
PLUMBING-Final 3/19/2026 Approved VINCENT HANLEY
Service/Power Release 3/19/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 3/19/2026 Not Ready for Inspection VINCENT HANLEY