342-342 1/4 N BREED ST 90033

Certificate Information: 342-342 1/4 N BREED ST 90033

Application / Permit
25010-20000-01214
Plan Check / Job No.
B25VN07765
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 DETACHED 2-STORY ACCESSORY DWELLING UNIT (NORTH) TO COMPLY WITH GCS 66323(a)(4) PER ENGINEERING
Permit Issued
Issued on 4/22/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 ALFRED RAMIREZ
Corrections Issued 3/29/2025 ALFRED RAMIREZ
Quality Review Completed 4/2/2025 STEVEN KIM
Building Plans Picked Up 4/2/2025 APPLICANT
Plan Check Approved 4/22/2025 ALFRED RAMIREZ
Issued 4/22/2025 APPLICANT
CofO in Progress 1/5/2026 ALIZAH MAYAGOITIA
Permit Finaled 1/5/2026 DEROLD HAUFF
CofO Issued 1/5/2026 DEROLD HAUFF
Permit Finaled 1/5/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/2/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/2/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 4/2/2025 JEANIE LAM
Sewer availability Cleared 4/2/2025 JEANIE LAM
Clean Up Green Up Cleared 4/3/2025 DORIAN AGUILAR
Miscellaneous Cleared 4/3/2025 DORIAN AGUILAR
ZA Case Cleared 4/3/2025 DORIAN AGUILAR
ZI Cleared 4/3/2025 DORIAN AGUILAR
GPI Written Notices Cleared 4/22/2025 ALFRED RAMIREZ
Grading Pre-Inspection Cleared 4/22/2025 ALFRED RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2025 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 5/27/2025 Partial Approval ALIZAH MAYAGOITIA
Sewer 5/27/2025 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/30/2025 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/30/2025 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 5/30/2025 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 5/30/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 7/9/2025 Partial Approval JUSTIN HAWLEY
Gas Test 7/22/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 7/22/2025 Not Ready for Inspection JOHN QUINTANILLA
Rough-Elec/Plmb/HVAC 7/22/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 8/11/2025 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Approved OSVALDO PARAMO
Green Building Rough 8/11/2025 Not Ready for Inspection OSVALDO PARAMO
METHANE-Rough 8/11/2025 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 8/11/2025 Corrections Issued OSVALDO PARAMO
Verify Sprinkler Sign Off 8/11/2025 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 8/13/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/22/2025 Approved ANTHONY RAMOS
Insulation 8/22/2025 Approved ANTHONY RAMOS
Drywall Nailing 9/4/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/4/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/4/2025 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/9/2025 Partial Approval ANTHONY RAMOS
Interior/Exterior Lathing 9/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/3/2025 Approved ALIZAH MAYAGOITIA
Final 10/28/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 10/28/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 10/28/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 10/28/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 11/12/2025 Corrections Issued ALIZAH MAYAGOITIA
Final 11/20/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 11/20/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 11/20/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 11/20/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/26/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 11/26/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 11/26/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/12/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/29/2025 Approved ALIZAH MAYAGOITIA
Final 1/2/2026 OK to Issue CofO ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/2/2026 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 1/2/2026 Approved ALIZAH MAYAGOITIA