15123 W OTSEGO ST 91403

Certificate Information: 15123 W OTSEGO ST 91403

Application / Permit
25010-20000-01176
Plan Check / Job No.
B25VN07412
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED, ALL ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k). WORK DONE PER ARCHITECT DESIGN.
Permit Issued
Issued on 7/23/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2025 APPLICANT
Assigned to Plan Check Engineer 3/25/2025 JESSE ARELLANO
Corrections Issued 3/26/2025 JESSE ARELLANO
Building Plans Picked Up 4/2/2025 APPLICANT
Plan Check Approved 5/6/2025 MADISON O'DELL
Issued 7/23/2025 APPLICANT
CofO in Progress 2/13/2026 JACK KARGODORIAN
Permit Finaled 3/10/2026 RUBEN SALAS
CofO Issued 3/10/2026 RUBEN SALAS
Permit Finaled 3/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/27/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 4/27/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 4/27/2025 TAL SHEMEN
Sewer availability Cleared 4/27/2025 TAL SHEMEN
ZI Cleared 5/1/2025 JACQUELINE TORRES

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Idea Fix Construction; Lic. No.: 906459-B 7715 SEDAN AVE      WEST HILLS, CA 91304

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/31/2025 Partial Approval JACK KARGODORIAN
Underground Mechanical 7/31/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 8/5/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 8/13/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 9/29/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 10/1/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Approved DAVID ANDERSON
Green Building Rough 10/1/2025 Approved DAVID ANDERSON
PLUMBING-Rough 10/1/2025 Corrections Issued DAVID ANDERSON
Verify Sprinkler Sign Off 10/1/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/6/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/6/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 10/6/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/9/2025 Approved JACK KARGODORIAN
Insulation 10/16/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 10/16/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 10/23/2025 Approved JACK KARGODORIAN
Final 1/8/2026 Corrections Issued RYAN SALAZAR
Green Building Final 1/8/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Not Ready RYAN SALAZAR
Service/Power Release 1/8/2026 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 1/8/2026 Approved RYAN SALAZAR
Final 2/4/2026 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved JACK KARGODORIAN
Service/Power Release 2/4/2026 Not Ready for Inspection JACK KARGODORIAN
Final 2/9/2026 Corrections Issued JACK KARGODORIAN
Service/Power Release 2/9/2026 Not Ready for Inspection JACK KARGODORIAN
Final 2/12/2026 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 2/12/2026 Approved JACK KARGODORIAN