301-303 S ROCKINGHAM AVE 90049
Certificate Information: 301-303 S ROCKINGHAM AVE 90049
- Application / Permit
- 25010-20000-01166
- Plan Check / Job No.
- B25VN07365
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 81'-9" X 106'-1.5" 2-STORY IRREGUALR SHAPED SFD W/ ACCESSORY DWELLING UNIT per GC 66323(a)(1) & 3-CAR GARAGE OVER BASEMENT. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 3/20/2025 | KAITA SAITO |
| Corrections Issued | 3/25/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 3/25/2025 | STEVEN KIM |
| Building Plans Picked Up | 3/26/2025 | APPLICANT |
| Applicant returned to address corrections | 4/22/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 6/10/2025 | RAPHAEL ROSAS |
| Issued | 6/10/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/28/2025 | KURT CORRAL |
| Address approval | Cleared | 4/1/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/1/2025 | HISASHI KOBAYAKAWA |
| CPC | Cleared | 4/3/2025 | BRENNEN OBETO |
| Low Impact Development (LID) | Cleared | 4/4/2025 | LUIS LUVANO |
| Frnt yard landscape/Water mgmt | Cleared | 4/8/2025 | BRENNEN OBETO |
| Trees in Parkway | Cleared | 5/21/2025 | MIGUEL ORNELAS |
| Specific Plan | Cleared | 5/22/2025 | PEDRO AYALA |
| Permit | Cleared | 5/23/2025 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 5/23/2025 | KIMBERLY HERNANDEZ |
| Miscellaneous | Cleared | 6/5/2025 | BRENNEN OBETO |
| Zoning Plan Check | Cleared | 6/5/2025 | RAPHAEL ROSAS |
| GPI Written Notices | Cleared | 6/10/2025 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 6/10/2025 | RAPHAEL ROSAS |
Contact Information
| Contractor | E T Development Inc; Lic. No.: 994749-B | 7256 BELLAIRE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Daneshfar,, Kourosh; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Danz,, Joshua; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | Tani,, Jason; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/12/2025 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Rough | 7/17/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 7/31/2025 | Partial Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 8/1/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 8/15/2025 | Partial Approval | HERBERT GIRON |
| Deputy Shotcrete | 8/18/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 9/30/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 10/1/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/15/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 10/17/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 10/20/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 12/17/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Wood Construction | 1/28/2026 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 1/30/2026 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 1/30/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 2/2/2026 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/3/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 2/6/2026 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/6/2026 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 2/12/2026 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 2/19/2026 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 2/19/2026 | Approved | HERBERT GIRON |
| Shower Pan | 3/4/2026 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/16/2026 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/6/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/7/2026 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 4/7/2026 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/7/2026 | Partial Approval | HERBERT GIRON |
| Special/Order Compliance | 4/7/2026 | Corrections Issued | HERBERT GIRON |
| Verify Sprinkler Sign Off | 4/7/2026 | Corrections Issued | HERBERT GIRON |
| Insulation | 4/14/2026 | Corrections Issued | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 4/14/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/27/2026 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/30/2026 | Approved | HERBERT GIRON |