10023 N ALDEA AVE 91325
Certificate Information: 10023 N ALDEA AVE 91325
- Application / Permit
- 25010-20000-01163
- Plan Check / Job No.
- B25VN07360
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ALL ELECTRIC ACCESSORY DWELLING UNIT AND COVERED PORCH PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/16/2025
- Issuing Office
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 3/26/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/1/2025 | APPLICANT |
| Plan Check Approved | 6/13/2025 | YAQUB MIRZA |
| Issued | 6/16/2025 | APPLICANT |
| CofO in Progress | 12/26/2025 | KEVIN BERBERYAN |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/14/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/14/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/15/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/6/2025 | GEVORK KARAPETYAN |
| GPI Written Notices | Cleared | 6/13/2025 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 6/13/2025 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 7/28/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 8/5/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/7/2025 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 8/8/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/8/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 8/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/27/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/29/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/10/2025 | Conditional Approval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 9/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 9/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 9/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 9/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 9/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 9/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/16/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 9/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 9/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 12/24/2025 | Approved | KEVIN BERBERYAN |
| Final | 12/24/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/24/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 12/24/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 12/24/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/24/2025 | Approved | KEVIN BERBERYAN |