10023 N ALDEA AVE 91325

Certificate Information: 10023 N ALDEA AVE 91325

Application / Permit
25010-20000-01163
Plan Check / Job No.
B25VN07360
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ALL ELECTRIC ACCESSORY DWELLING UNIT AND COVERED PORCH PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/16/2025
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2025 APPLICANT
Assigned to Plan Check Engineer 3/24/2025 JEROME MAGAT PALMA
Corrections Issued 3/26/2025 JEROME MAGAT PALMA
Building Plans Picked Up 4/1/2025 APPLICANT
Plan Check Approved 6/13/2025 YAQUB MIRZA
Issued 6/16/2025 APPLICANT
CofO in Progress 12/26/2025 KEVIN BERBERYAN
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/14/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/14/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/14/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/15/2025 LEE GUILBEAUX
Sewer availability Cleared 4/15/2025 LEE GUILBEAUX
Construction near power lines Cleared 5/6/2025 GEVORK KARAPETYAN
GPI Written Notices Cleared 6/13/2025 JEROME MAGAT PALMA
Grading Pre-Inspection Cleared 6/13/2025 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2025 Approved NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 7/14/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/14/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/16/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 7/28/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 8/5/2025 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 8/5/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 8/7/2025 Corrections Issued MISAEL ESPARZA
Insulation 8/8/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/8/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval NICHOLAS TROWBRIDGE
HVAC-Rough 8/25/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 8/27/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 8/29/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 9/10/2025 Conditional Approval NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 9/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 9/10/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 9/10/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 9/12/2025 Approved NICHOLAS TROWBRIDGE
Sewer 9/12/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 9/12/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/16/2025 Partial Approval NICHOLAS TROWBRIDGE
Insulation 9/18/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 9/25/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/25/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/24/2025 Approved KEVIN BERBERYAN
Final 12/24/2025 OK to Issue CofO KEVIN BERBERYAN
Footing/Foundation/Slab 12/24/2025 Approved KEVIN BERBERYAN
Green Building Final 12/24/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 12/24/2025 Approved KEVIN BERBERYAN
Smoke Detectors 12/24/2025 Approved KEVIN BERBERYAN