13058 W LORNE ST 91605

Certificate Information: 13058 W LORNE ST 91605

Application / Permit
25010-20000-01154
Plan Check / Job No.
B25VN07281
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. NEW TWO STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 6/24/2025
Issuing Office
Current Status
Issued on 6/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 VU NGUYEN
Corrections Issued 4/10/2025 VU NGUYEN
Quality Review Completed 4/10/2025 EUGENE BARBEAU
Applicant returned to address corrections 4/23/2025 VU NGUYEN
Plan Check Approved 6/24/2025 VU NGUYEN
Issued 6/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/18/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 4/18/2025 TAL SHEMEN
Sewer availability Cleared 4/22/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 4/23/2025 TAL SHEMEN
Construction near power lines Cleared 6/3/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Final 6/8/2026   
Final 6/8/2026   
PLUMBING-Final 6/8/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/11/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/28/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 8/28/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/29/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/29/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Approved VINCENT HANLEY
Green Building Rough 10/29/2025 Approved VINCENT HANLEY
HVAC-Rough 10/29/2025 Approved VINCENT HANLEY
PLUMBING-Rough 10/29/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/4/2025 Partial Approval DAVID MATSON
Insulation 11/17/2025 Approved CHRISTOPHER MORFIN
Shower Pan 11/20/2025 Approved JOSE AVILA
Drywall Nailing 12/4/2025 Approved LOUIS ESCOTO
Sewer 2/2/2026 No Access for Inspection OGANES TARAKHCHYAN
Underground Mechanical 2/2/2026 No Access for Inspection OGANES TARAKHCHYAN
Sewer 2/4/2026 Approved OGANES TARAKHCHYAN
Underground Mechanical 2/4/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/27/2026 Approved OGANES TARAKHCHYAN
Final 4/27/2026 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 4/27/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Final 4/27/2026 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 4/27/2026 Approved OGANES TARAKHCHYAN
Smoke Detectors 4/27/2026 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 4/27/2026 Approved OGANES TARAKHCHYAN
Final 5/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN