13058 W LORNE ST 91605
Certificate Information: 13058 W LORNE ST 91605
- Application / Permit
- 25010-20000-01154
- Plan Check / Job No.
- B25VN07281
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW TWO STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- Issued on 6/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2025 | VU NGUYEN |
| Corrections Issued | 4/10/2025 | VU NGUYEN |
| Quality Review Completed | 4/10/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 4/23/2025 | VU NGUYEN |
| Plan Check Approved | 6/24/2025 | VU NGUYEN |
| Issued | 6/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 4/18/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 4/22/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2025 | TAL SHEMEN |
| Construction near power lines | Cleared | 6/3/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Final | 6/8/2026 |
| Final | 6/8/2026 |
| PLUMBING-Final | 6/8/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/11/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/28/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 8/28/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/29/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/29/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/29/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/29/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/29/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/4/2025 | Partial Approval | DAVID MATSON |
| Insulation | 11/17/2025 | Approved | CHRISTOPHER MORFIN |
| Shower Pan | 11/20/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 12/4/2025 | Approved | LOUIS ESCOTO |
| Sewer | 2/2/2026 | No Access for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/2/2026 | No Access for Inspection | OGANES TARAKHCHYAN |
| Sewer | 2/4/2026 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/4/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/27/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 4/27/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 4/27/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/27/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 4/27/2026 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/27/2026 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/27/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 5/6/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |