6175 N KENWATER AVE 91367

Certificate Information: 6175 N KENWATER AVE 91367

Application / Permit
25010-20000-01123
Plan Check / Job No.
B25VN07055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 21' X 29' IRREGULAR SHAPED 2-STORY SFD per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/30/2025
Issuing Office
Current Status
CofO in Progress on 6/11/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/14/2025 APPLICANT
Assigned to Zoning Architect 3/20/2025 BENNY WONG
Assigned to Plan Check Engineer 3/27/2025 RAPHAEL ROSAS
Corrections Issued 4/8/2025 RAPHAEL ROSAS
Quality Review Completed 4/10/2025 STEVEN KIM
Building Plans Picked Up 4/14/2025 APPLICANT
Applicant returned to address corrections 7/29/2025 RAPHAEL ROSAS
Plan Check Approved 7/30/2025 RAPHAEL ROSAS
Issued 7/30/2025 APPLICANT
CofO in Progress 6/11/2026 TROY SANDERS

Permit Application Clearance Information

Address approval Cleared 4/18/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 4/18/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 4/23/2025 TAL SHEMEN
Sewer availability Cleared 4/23/2025 TAL SHEMEN
Hydrant and Access approval Cleared 5/2/2025 KURT CORRAL
Senate Bill 9 Cleared 7/17/2025 DANIEL CORONADO
Zoning Plan Check Cleared 7/17/2025 BENNY WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/12/2025 Partial Approval TROY SANDERS
Footing/Foundation/Slab 8/18/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 10/28/2025 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 10/28/2025 Approved TROY SANDERS
Green Building Rough 10/28/2025 Approved TROY SANDERS
HVAC-Rough 10/28/2025 Approved TROY SANDERS
PLUMBING-Rough 10/28/2025 Approved TROY SANDERS
Verify Sprinkler Sign Off 10/28/2025 Not Ready for Inspection TROY SANDERS
Deputy Wood Construction 11/5/2025 Conditional Approval ROBERT GOLD
Interior/Exterior Lathing 11/17/2025 Approved TROY SANDERS
Shower Pan 11/17/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 11/25/2025 Approved TROY SANDERS
Insulation 11/25/2025 Approved TROY SANDERS
Verify Sprinkler Sign Off 11/25/2025 Approved TROY SANDERS
Drywall Nailing 12/3/2025 Approved TROY SANDERS
ELECTRICAL-Final 2/19/2026 Approved TROY SANDERS
Final 2/19/2026 Corrections Issued TROY SANDERS
Green Building Final 2/19/2026 Not Ready for Inspection TROY SANDERS
HVAC-Final 2/19/2026 Approved TROY SANDERS
PLUMBING-Final 2/19/2026 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Approved TROY SANDERS
Service/Power Release 2/19/2026 Approved TROY SANDERS
Smoke Detectors 2/19/2026 Approved TROY SANDERS
Final 6/10/2026 OK to Issue CofO TROY SANDERS
Green Building Final 6/10/2026 Approved TROY SANDERS