10537 N JORDAN AVE 91311

Certificate Information: 10537 N JORDAN AVE 91311

Application / Permit
25010-20000-01117
Plan Check / Job No.
B25VN07026
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/17/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 JEROME MAGAT PALMA
Corrections Issued 3/22/2025 JEROME MAGAT PALMA
Building Plans Picked Up 3/24/2025 APPLICANT
Applicant returned to address corrections 9/16/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 11/17/2025 SERGIO MUNIZ
Issued 11/17/2025 APPLICANT
CofO in Progress 4/27/2026 JEFFREY HARTLINE
Permit Finaled 4/28/2026 JOHN JANSON
CofO Issued 4/28/2026 JOHN JANSON
Permit Finaled 4/28/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/24/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/24/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/24/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/26/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 9/9/2025 CHARLES POWELL
Miscellaneous Cleared 9/15/2025 DORIAN AGUILAR
GPI Written Notices Cleared 11/4/2025 JEROME MAGAT PALMA

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B 12005 ALBERS APT 233      NORTH HOLLYWOOD, CA 91607

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/19/2025 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/22/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/16/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 1/16/2026 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 1/16/2026 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/20/2026 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/20/2026 Approved CHRIS CHRISTENSEN
HVAC-Rough 1/20/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 1/20/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/30/2026 Partial Approval KRISTEN CAUSEY
Shower Pan 1/30/2026 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/4/2026 Approved CHRIS CHRISTENSEN
Green Building Rough 2/4/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/4/2026 Partial Approval CHRIS CHRISTENSEN
Insulation 2/11/2026 Conditional Approval CHRIS CHRISTENSEN
Drywall Nailing 2/13/2026 Approved HENRY KIM
Insulation 2/13/2026 Approved HENRY KIM
ELECTRICAL-Final 4/20/2026 Approved JEFFREY HARTLINE
Final 4/20/2026 Corrections Issued JEFFREY HARTLINE
Green Building Final 4/20/2026 Approved JEFFREY HARTLINE
HVAC-Final 4/20/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 4/20/2026 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 4/20/2026 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 4/20/2026 Approved JEFFREY HARTLINE
Final 4/24/2026 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 4/24/2026 Approved JEFFREY HARTLINE