10537 N JORDAN AVE 91311
Certificate Information: 10537 N JORDAN AVE 91311
- Application / Permit
- 25010-20000-01117
- Plan Check / Job No.
- B25VN07026
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/17/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 3/22/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/24/2025 | APPLICANT |
| Applicant returned to address corrections | 9/16/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 11/17/2025 | SERGIO MUNIZ |
| Issued | 11/17/2025 | APPLICANT |
| CofO in Progress | 4/27/2026 | JEFFREY HARTLINE |
| Permit Finaled | 4/28/2026 | JOHN JANSON |
| CofO Issued | 4/28/2026 | JOHN JANSON |
| Permit Finaled | 4/28/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/24/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/24/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 9/9/2025 | CHARLES POWELL |
| Miscellaneous | Cleared | 9/15/2025 | DORIAN AGUILAR |
| GPI Written Notices | Cleared | 11/4/2025 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Neo Builders And Design Inc; Lic. No.: 1114778-B | 12005 ALBERS APT 233 NORTH HOLLYWOOD, CA 91607 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/19/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/22/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/16/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/16/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/16/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/20/2026 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/20/2026 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/20/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/20/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/30/2026 | Partial Approval | KRISTEN CAUSEY |
| Shower Pan | 1/30/2026 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/4/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/4/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 2/11/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/13/2026 | Approved | HENRY KIM |
| Insulation | 2/13/2026 | Approved | HENRY KIM |
| ELECTRICAL-Final | 4/20/2026 | Approved | JEFFREY HARTLINE |
| Final | 4/20/2026 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 4/20/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 4/20/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 4/20/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 4/20/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 4/20/2026 | Approved | JEFFREY HARTLINE |
| Final | 4/24/2026 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 4/24/2026 | Approved | JEFFREY HARTLINE |