15811 W COMMUNITY ST 91343

Certificate Information: 15811 W COMMUNITY ST 91343

Application / Permit
25010-20000-01111
Plan Check / Job No.
B25VN06985
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 45' X 28' ONE STORY DWELLING UNIT PER SB9 WITH ATTACHED 10' X 19'-10" OPEN TRELLIS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/13/2025
Issuing Office
Current Status
Issued on 5/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/14/2025 APPLICANT
Assigned to Zoning Architect 3/20/2025 ERIC ROMERO
Assigned to Plan Check Engineer 3/27/2025 SELLA BENYAMIN
Corrections Issued 4/3/2025 SELLA BENYAMIN
Quality Review Completed 4/3/2025 STEVEN KIM
Building Plans Picked Up 4/4/2025 APPLICANT
Plan Check Approved 5/13/2025 SELLA BENYAMIN
Issued 5/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/1/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/1/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/8/2025 COLIN LOREDO
Sewer availability Cleared 4/8/2025 COLIN LOREDO
Senate Bill 9 Cleared 4/16/2025 JASON CHAN
Zoning Plan Check Cleared 5/8/2025 ERIC ROMERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/8/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 7/8/2025 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 7/14/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 7/14/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 8/18/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 8/19/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 8/19/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/27/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 8/27/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 8/27/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/27/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 8/27/2025 Approved GAREN HAYRAPETYAN
Insulation 9/3/2025 Corrections Issued GAREN HAYRAPETYAN
Insulation 9/5/2025 Approved WAYNE REGESTER
Shower Pan 9/5/2025 Approved WAYNE REGESTER
Drywall Nailing 9/9/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/9/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 12/12/2025 Partial Approval GAREN HAYRAPETYAN
Pre-Inspection 1/21/2026 Approved WAYNE REGESTER
Service/Power Release 1/21/2026 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 3/3/2026 Corrections Issued KIRK SANDERS
Service/Power Release 3/3/2026 Not Ready for Inspection KIRK SANDERS
HVAC-Final 3/5/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 4/3/2026 Approved KEVIN BERBERYAN
Final 4/3/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 4/3/2026 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 4/3/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 4/3/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 4/3/2026 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 4/3/2026 Approved KEVIN BERBERYAN
Final 4/22/2026 Conditional Approval KIRK SANDERS
Green Building Final 4/22/2026 Approved KIRK SANDERS
Service/Power Release 4/22/2026 Approved KIRK SANDERS