19522 W HEMMINGWAY ST 91335

Certificate Information: 19522 W HEMMINGWAY ST 91335

Application / Permit
25010-20000-01051
Plan Check / Job No.
B25VN06581
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW 2-STORY (24' x 21'-6") DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (b)(1)
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
CofO Issued on 4/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 EDWARD MEHRABIAN
Corrections Issued 4/1/2025 EDWARD MEHRABIAN
Quality Review Completed 4/6/2025 DAWN MC NULTY
Plan Check Approved 5/28/2025 EDWARD MEHRABIAN
Issued 6/4/2025 APPLICANT
CofO in Progress 4/9/2026 ARUTYUN MADATYAN
Permit Finaled 4/14/2026 JOHN JANSON
CofO Issued 4/14/2026 JOHN JANSON
Permit Finaled 4/14/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/12/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 4/12/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/17/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/17/2025 SAFA JAVANMARDI

Contact Information

Contractor Southeast Home Builders Inc; Lic. No.: 1055627-B       ,
Engineer Kashe,, Andrew; Lic. No.: C94117 984 SILVERTIP DR      DIAMOND BAR, CA 91765

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2025 Partial Inspection ARUTYUN MADATYAN
Sewer 7/31/2025 Approved ARUTYUN MADATYAN
Deputy Reinf. Concrete 8/19/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/26/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 8/26/2025 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 9/2/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 9/2/2025 Approved ARUTYUN MADATYAN
Grounding or Bonding 9/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2025 Corrections Issued KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 10/15/2025 Approved ARUTYUN MADATYAN
Green Building Rough 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
Grounding or Bonding 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 10/15/2025 Corrections Issued ARUTYUN MADATYAN
Shower Pan 10/15/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 10/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 10/20/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/20/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/21/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/28/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 10/28/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 10/28/2025 Approved ARUTYUN MADATYAN
Insulation 10/28/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 11/18/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/26/2026 Approved JACK KARGODORIAN
Final 3/26/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 3/26/2026 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 3/26/2026 Approved JACK KARGODORIAN
PLUMBING-Final 3/26/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 3/26/2026 Not Required JACK KARGODORIAN
Smoke Detectors 3/26/2026 Approved JACK KARGODORIAN
Service/Power Release 3/31/2026 Not Ready for Inspection JUAN ALVARADO
Final 4/3/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 4/3/2026 Approved ARUTYUN MADATYAN
Service/Power Release 4/3/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 4/8/2026 OK to Issue CofO ARUTYUN MADATYAN
Service/Power Release 4/8/2026 Approved ARUTYUN MADATYAN