8214 N SHADYGLADE AVE 91605

Certificate Information: 8214 N SHADYGLADE AVE 91605

Application / Permit
25010-20000-01012
Plan Check / Job No.
B25VN00577
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***ePlan *** New 2-story Dettahed Accessory Dwelling Unit per Ordinance LAMC 12.22 A.33(b)(1). Fully Sprinkled NFPA 13-D. No parking required per AB-2097 ---2 of 3 ---
Permit Issued
Issued on 7/10/2025
Issuing Office
Current Status
Issued on 7/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Zoning Architect 2/27/2025 BENNY WONG
Assigned to Plan Check Engineer 3/6/2025 MIROOSH KHACHATOORIAN
Corrections Issued 3/10/2025 EDWIN ESPIN
Quality Review Completed 3/13/2025 CHIHARU SUZUKI
Applicant returned to address corrections 3/27/2025 EDWIN ESPIN
Applicant returned to address corrections 5/20/2025 EDWIN ESPIN
Applicant returned to address corrections 5/29/2025 EDWIN ESPIN
Plan Check Approved 7/9/2025 EDWIN ESPIN
Issued 7/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/28/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 4/28/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 4/28/2025 MICHAEL BROWN
Sewer availability Cleared 4/28/2025 MICHAEL BROWN
Hydrant and Access approval Cleared 5/1/2025 PATRICK PEREZ
Construction near power lines Cleared 7/1/2025 GEVORK KARAPETYAN
Construction within easement Cleared 7/1/2025 GEVORK KARAPETYAN
Zoning Plan Check Cleared 7/3/2025 BENNY WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Azarmy,, Cyrus; Lic. No.: L9404 4402 CHARLEMONT AVE      WOODLAND HILLS, CA 91364
Engineer Khanlou,, Amir; Lic. No.: C87550 2603 BASIL LN      LOS ANGELES, CA 90077
Engineer Khanlou,, Amir; Lic. No.: NA87550       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/4/2025 Partial Approval MATTHEW NELSON
Underground Mechanical 9/4/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 10/22/2025 Approved MATTHEW NELSON
Deputy Steel/Welding 3/20/2026 Conditional Approval RAUL OLAGI
Deputy Steel/Welding 4/22/2026 Conditional Approval DAVID MATSON
Structural Steel Frame 4/24/2026 Partial Approval MATTHEW NELSON