8529 N AMESTOY AVE 91325
Certificate Information: 8529 N AMESTOY AVE 91325
- Application / Permit
- 25010-20000-01003
- Plan Check / Job No.
- B25VN05780
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 16' x 16' DET PATIO COVER (GAZEBO)
- Permit Issued
- Issued on 7/16/2025
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | SEAN SHAHMIRI |
| Assigned to Zoning Architect | 3/6/2025 | SARHAD GHEVANDIAN |
| Corrections Issued | 3/17/2025 | SEAN SHAHMIRI |
| Quality Review Completed | 3/18/2025 | STEVEN KIM |
| Applicant returned to address corrections | 6/10/2025 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/25/2025 | SEAN SHAHMIRI |
| Plan Check Approved | 7/1/2025 | SEAN SHAHMIRI |
| Issued | 7/16/2025 | APPLICANT |
| CofO in Progress | 2/4/2026 | KEVIN BERBERYAN |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/9/2025 | DANIEL CORONADO |
| ZA Case | Cleared | 5/9/2025 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 5/19/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/19/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2025 | ABEL CASILLAS |
| Zoning Plan Check | Cleared | 6/17/2025 | SARHAD GHEVANDIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 8/11/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 8/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 9/17/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/20/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/20/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 10/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 10/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/29/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 10/29/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 10/29/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 11/4/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 11/6/2025 | Approved | CHRISTOPHER MORFIN |
| Shower Pan | 11/6/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 11/14/2025 | Approved | CHRISTOPHER MORFIN |
| Underground Mechanical | 1/9/2026 | Approved | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 1/23/2026 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 1/23/2026 | Approved | KEVIN BERBERYAN |
| Final | 1/28/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 1/28/2026 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Required | KIRK SANDERS |
| Service/Power Release | 1/28/2026 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 1/28/2026 | Approved | KIRK SANDERS |
| Final | 2/3/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 2/3/2026 | Not Required | KEVIN BERBERYAN |