9648-9650 N BARTEE AVE 91331

Certificate Information: 9648-9650 N BARTEE AVE 91331

Application / Permit
25010-20000-00982
Plan Check / Job No.
B25VN05923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE 13'X36' TWO STORY ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33(c) and (e)) AND PATIO COVER ADDITION AT REAR OF (E) ONE STORY SFD WITH ATTACHED ONE CAR GARAGE WITH ENTRY PORCH.
Permit Issued
Issued on 6/23/2025
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 DAWN MC NULTY
Corrections Issued 4/6/2025 DAWN MC NULTY
Quality Review Completed 4/18/2025 OMID HEDAYAT
Applicant returned to address corrections 5/21/2025 DAWN MC NULTY
Plan Check Approved 6/12/2025 DAWN MC NULTY
Plan Check Approved 6/18/2025 DAWN MC NULTY
Plan Check Approved 6/21/2025 DAWN MC NULTY
Issued 6/23/2025 APPLICANT
CofO in Progress 1/16/2026 MICHEL ABAJAN
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/27/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/27/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/27/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/9/2025 LEE GUILBEAUX
Sewer availability Cleared 5/9/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Phan,, Phillip Trung Tri; Lic. No.: NA76425       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/8/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/17/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval MICHEL ABAJAN
Underground Mechanical 9/9/2025 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 9/19/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Rough 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
MERV13>=Rough 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 9/22/2025 Corrections Issued NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 9/29/2025 Approved KEVIN BERBERYAN
Insulation 10/1/2025 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 10/1/2025 Partial Approval MICHAEL CORTEZ
Insulation 10/8/2025 Approved MICHEL ABAJAN
Drywall Nailing 10/15/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/15/2025 Approved MICHEL ABAJAN
Gas Test 12/9/2025 Approved MICHEL ABAJAN
Underground Mechanical 12/9/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/15/2026 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/15/2026 Approved MICHEL ABAJAN
Final 1/15/2026 OK to Issue CofO MICHEL ABAJAN
Green Building Final 1/15/2026 Approved MICHEL ABAJAN
Green Building Rough 1/15/2026 Approved MICHEL ABAJAN
HVAC-Final 1/15/2026 Approved MICHEL ABAJAN
MERV13>=Final 1/15/2026 Approved MICHEL ABAJAN
MERV13>=Rough 1/15/2026 Approved MICHEL ABAJAN
PLUMBING-Final 1/15/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/15/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/15/2026 Approved MICHEL ABAJAN