9648-9650 N BARTEE AVE 91331
Certificate Information: 9648-9650 N BARTEE AVE 91331
- Application / Permit
- 25010-20000-00982
- Plan Check / Job No.
- B25VN05923
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 13'X36' TWO STORY ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33(c) and (e)) AND PATIO COVER ADDITION AT REAR OF (E) ONE STORY SFD WITH ATTACHED ONE CAR GARAGE WITH ENTRY PORCH.
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | DAWN MC NULTY |
| Corrections Issued | 4/6/2025 | DAWN MC NULTY |
| Quality Review Completed | 4/18/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/21/2025 | DAWN MC NULTY |
| Plan Check Approved | 6/12/2025 | DAWN MC NULTY |
| Plan Check Approved | 6/18/2025 | DAWN MC NULTY |
| Plan Check Approved | 6/21/2025 | DAWN MC NULTY |
| Issued | 6/23/2025 | APPLICANT |
| CofO in Progress | 1/16/2026 | MICHEL ABAJAN |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
| CofO Issued | 1/28/2026 | RUBEN SALAS |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/27/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/27/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/9/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: NA76425 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/8/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/17/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 9/9/2025 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 9/19/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/22/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Green Building Rough | 9/22/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| MERV13>=Rough | 9/22/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 9/22/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 9/29/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 10/1/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 10/1/2025 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 10/8/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/15/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/15/2025 | Approved | MICHEL ABAJAN |
| Gas Test | 12/9/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 12/9/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/15/2026 | Approved | MICHEL ABAJAN |
| Final | 1/15/2026 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 1/15/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/15/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/15/2026 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 1/15/2026 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 1/15/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/15/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/15/2026 | Approved | MICHEL ABAJAN |