13210 N HERRICK AVE 91342
Certificate Information: 13210 N HERRICK AVE 91342
- Application / Permit
- 25010-20000-00963
- Plan Check / Job No.
- B25VN02652
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: NEW 1-STORY (58'-5" X 24'-3") SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND PORCH PER SB9 TWO-UNIT DEVELOPMENT CA GOVT. CODE 65852.21. NFPA 13R FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 11/2/2025
- Issuing Office
- Current Status
- Issued on 11/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | VAHAN JIVALAGIAN |
| Corrections Issued | 3/4/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 3/7/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/3/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/17/2025 | VAHAN JIVALAGIAN |
| Issued | 11/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/4/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/4/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/8/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 7/1/2025 | JERRY KAO |
| Senate Bill 9 | Cleared | 9/4/2025 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hazrati,, Kayvan Naghib; Lic. No.: C60556 | 12021 ELNORA PLACE GRANADA HILLS, CA 91344 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/9/2026 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/20/2026 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/24/2026 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/24/2026 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 3/24/2026 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 3/24/2026 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 3/24/2026 | Corrections Issued | DAVID ANDERSON |
| Sewer | 3/24/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 3/24/2026 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 3/24/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/31/2026 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 3/31/2026 | Approved | KEVIN BERBERYAN |
| Sewer | 3/31/2026 | Approved | KEVIN BERBERYAN |
| Wood Frame | 3/31/2026 | Conditional Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/6/2026 | Approved | MICHEL ABAJAN |
| Shower Pan | 4/6/2026 | Approved | MICHEL ABAJAN |
| Insulation | 4/9/2026 | Approved | JOSE AVILA |
| Drywall Nailing | 4/16/2026 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 4/16/2026 | Approved | KEVIN BERBERYAN |