11954 W REDBANK ST 91352
Certificate Information: 11954 W REDBANK ST 91352
- Application / Permit
- 25010-20000-00942
- Plan Check / Job No.
- B25VN05589
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k).
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 3/6/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/10/2025 | APPLICANT |
| Applicant returned to address corrections | 4/28/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/13/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/2/2025 | ROSENDO MEDINA |
| Issued | 6/2/2025 | APPLICANT |
| CofO in Progress | 1/26/2026 | MATTHEW NELSON |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/14/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/14/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/4/2025 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/6/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/6/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 6/23/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 6/23/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/25/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/25/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/25/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/26/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 6/27/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/27/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/30/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 6/30/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/30/2025 | Approved | MATTHEW NELSON |
| Service/Power Release | 6/30/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 7/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/3/2025 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 7/3/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/3/2025 | Partial Approval | MATTHEW NELSON |
| Insulation | 7/9/2025 | Corrections Issued | MATTHEW NELSON |
| Drywall Nailing | 7/14/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 7/21/2025 | Approved | MICHAEL CORTEZ |
| Gas Test | 7/25/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 7/25/2025 | Corrections Issued | MATTHEW NELSON |
| Gas Test | 7/28/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 7/28/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 7/30/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 7/30/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/1/2025 | Approved | MATTHEW NELSON |
| Service/Power Release | 8/18/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 8/18/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 8/21/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 8/21/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 8/21/2025 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 11/21/2025 | No Access for Inspection | DAVID ANDERSON |
| Gas Test | 12/3/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/3/2025 | Approved | MATTHEW NELSON |
| Service/Power Release | 12/3/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 12/12/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Service/Power Release | 12/12/2025 | Corrections Issued | MATTHEW NELSON |
| Gas Test | 12/26/2025 | No Access for Inspection | CRAIG DAVIS |
| Service/Power Release | 12/26/2025 | No Access for Inspection | CRAIG DAVIS |
| Gas Test | 12/30/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Service/Power Release | 12/30/2025 | Corrections Issued | MATTHEW NELSON |
| Gas Test | 1/5/2026 | Approved | MATTHEW NELSON |
| Service/Power Release | 1/5/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | MATTHEW NELSON |
| Final | 1/6/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 1/6/2026 | Approved | MATTHEW NELSON |
| MERV13>=Final | 1/6/2026 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 1/6/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 1/6/2026 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 1/6/2026 | Approved | MATTHEW NELSON |
| Final | 1/23/2026 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/23/2026 | SGSOV Approved | MATTHEW NELSON |