13217-13219 W STAGG ST 91605
Certificate Information: 13217-13219 W STAGG ST 91605
- Application / Permit
- 25010-20000-00920
- Plan Check / Job No.
- B25VN05492
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: PROPOSED IRREGULAR SHAPED SINGLE-FAMILY DWELLING PER SB9 AND ATTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A), NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT,ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Current Status
- CofO Issued on 7/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2025 | APPLICANT |
| Assigned to Zoning Architect | 3/6/2025 | FRANCIS AHN |
| Assigned to Plan Check Engineer | 3/13/2025 | RARES BODEA |
| Corrections Issued | 3/21/2025 | RARES BODEA |
| Quality Review Completed | 4/2/2025 | STEVEN KIM |
| Applicant returned to address corrections | 6/26/2025 | RARES BODEA |
| Applicant returned to address corrections | 8/11/2025 | RARES BODEA |
| Plan Check Approved | 8/19/2025 | RARES BODEA |
| Issued | 8/19/2025 | APPLICANT |
| CofO in Progress | 6/1/2026 | OGANES TARAKHCHYAN |
| CofO Issued | 7/8/2026 | RUBEN SALAS |
| Permit Finaled | 7/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2025 | JESUS LUNA |
| Roof/Waste drainage to street | Cleared | 4/7/2025 | JESUS LUNA |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | JESUS LUNA |
| Sewer availability | Cleared | 5/7/2025 | JESUS LUNA |
| Construction near power lines | Cleared | 5/13/2025 | GEVORK KARAPETYAN |
| Senate Bill 9 | Cleared | 5/16/2025 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 5/26/2025 | PATRICK PEREZ |
| Zoning Plan Check | Cleared | 6/18/2025 | Ricardo Ramirez Solis |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakobyan,, Sevak; Lic. No.: C96829 | 10238 LANGMUIR AVENUE SUNLAND, CA 91040 |
| Engineer | Hakobyan,, Sevak; Lic. No.: NA96829 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/27/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/4/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 11/26/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 11/26/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 12/1/2025 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 12/2/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/2/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/2/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/4/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/11/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 12/11/2025 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 12/11/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/18/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Insulation | 1/6/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/6/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/13/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/13/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 1/13/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/23/2026 | Approved | VINCENT HANLEY |
| Sewer | 3/16/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 5/27/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 5/27/2026 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/27/2026 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/27/2026 | Approved | OGANES TARAKHCHYAN |