13217-13219 W STAGG ST 91605

Certificate Information: 13217-13219 W STAGG ST 91605

Application / Permit
25010-20000-00920
Plan Check / Job No.
B25VN05492
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: PROPOSED IRREGULAR SHAPED SINGLE-FAMILY DWELLING PER SB9 AND ATTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A), NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT,ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/19/2025
Issuing Office
Current Status
CofO Issued on 7/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2025 APPLICANT
Assigned to Zoning Architect 3/6/2025 FRANCIS AHN
Assigned to Plan Check Engineer 3/13/2025 RARES BODEA
Corrections Issued 3/21/2025 RARES BODEA
Quality Review Completed 4/2/2025 STEVEN KIM
Applicant returned to address corrections 6/26/2025 RARES BODEA
Applicant returned to address corrections 8/11/2025 RARES BODEA
Plan Check Approved 8/19/2025 RARES BODEA
Issued 8/19/2025 APPLICANT
CofO in Progress 6/1/2026 OGANES TARAKHCHYAN
CofO Issued 7/8/2026 RUBEN SALAS
Permit Finaled 7/8/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/7/2025 JESUS LUNA
Roof/Waste drainage to street Cleared 4/7/2025 JESUS LUNA
Eng Process Fee Ord 176,300 Cleared 5/7/2025 JESUS LUNA
Sewer availability Cleared 5/7/2025 JESUS LUNA
Construction near power lines Cleared 5/13/2025 GEVORK KARAPETYAN
Senate Bill 9 Cleared 5/16/2025 DANIEL CORONADO
Hydrant and Access approval Cleared 5/26/2025 PATRICK PEREZ
Zoning Plan Check Cleared 6/18/2025 Ricardo Ramirez Solis

Contact Information

Contractor Owner-Builder       ,
Engineer Hakobyan,, Sevak; Lic. No.: C96829 10238 LANGMUIR AVENUE      SUNLAND, CA 91040
Engineer Hakobyan,, Sevak; Lic. No.: NA96829       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/27/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 9/4/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/19/2025 Partial Approval VINCENT HANLEY
Green Building Rough 11/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 11/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Wood Construction 12/1/2025 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 12/2/2025 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 12/2/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/2/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/4/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/11/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 12/11/2025 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 12/11/2025 Approved OGANES TARAKHCHYAN
Insulation 12/18/2025 Not Ready for Inspection LOUIS ESCOTO
Insulation 1/6/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/6/2026 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 1/13/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/13/2026 Approved OGANES TARAKHCHYAN
Shower Pan 1/13/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/23/2026 Approved VINCENT HANLEY
Sewer 3/16/2026 Approved OGANES TARAKHCHYAN
Final 5/27/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 5/27/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/27/2026 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 5/27/2026 Approved OGANES TARAKHCHYAN
Smoke Detectors 5/27/2026 Approved OGANES TARAKHCHYAN