362 N COPA DE ORO ROAD 90077

Certificate Information: 362 N COPA DE ORO ROAD 90077

Application / Permit
25010-20000-00903
Plan Check / Job No.
B25VN05343
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW IRREGULAR SHAPED DETACHED 1-STORY 32'-0" x 26'-9" RECREATION ROOM PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 5/6/2025
Issuing Office
Current Status
Issued on 5/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 ALFRED RAMIREZ
Corrections Issued 3/8/2025 ALFRED RAMIREZ
Quality Review Completed 3/13/2025 STEVEN KIM
Building Plans Picked Up 3/14/2025 APPLICANT
Plan Check Approved 5/6/2025 ALFRED RAMIREZ
Issued 5/6/2025 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 3/7/2025 ALFRED RAMIREZ
Grading Pre-Inspection Cleared 3/7/2025 ALFRED RAMIREZ
BHO/Hillside ordinance Cleared 3/18/2025 DARIN LAM
BHO/Hillside ordinance Cleared 3/18/2025 DARIN LAM
BHO/Hillside ordinance Cleared 3/18/2025 DARIN LAM
BHO/Hillside ordinance Cleared 3/18/2025 DARIN LAM
BHO/Hillside ordinance Cleared 3/18/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/18/2025 DARIN LAM
Sewer availability Cleared 3/18/2025 DARIN LAM
Low Impact Development (LID) Cleared 3/31/2025 MICHAEL SCADUTO
ZA Case Cleared 4/2/2025 MAYELA VILLA
ZA Case Cleared 4/2/2025 MAYELA VILLA
Roof/Waste drainage to street Cleared 4/9/2025 DIANA RENTERIA
Hydrant and Access approval Cleared 4/24/2025 JERRY KAO

Contact Information

Contractor B T C Builders Inc; Lic. No.: 743191-B 11373 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/26/2026 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/26/2026 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/1/2026 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/26/2026 Approved RYAN SALAZAR
ELECTRICAL-Rough 6/22/2026 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/22/2026 Approved CARLOS MATAMOROS
HVAC-Rough 6/22/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/22/2026 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/30/2026 Partial Approval DAVID SCANTLIN