19441 W VANOWEN ST 91335
Certificate Information: 19441 W VANOWEN ST 91335
- Application / Permit
- 25010-20000-00889
- Plan Check / Job No.
- B25VN05248
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW TWO-STORY DETACHED ADU PER CITY ORDINANCE. WORK DONE PER ENGINEER
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | KHUONG TRUONG |
| Corrections Issued | 3/25/2025 | KHUONG TRUONG |
| Quality Review Completed | 3/26/2025 | GARO TELMI |
| Plan Check Approved | 5/14/2025 | KHUONG TRUONG |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 3/10/2026 | JUAN ALVARADO |
| Permit Finaled | 3/12/2026 | JOHN JANSON |
| CofO Issued | 3/12/2026 | JOHN JANSON |
| Permit Finaled | 3/12/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/9/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/9/2025 | BIAINA HARITUNIAN |
| ZI | Cleared | 4/14/2025 | YINGSHI HUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/5/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Underground Mechanical | 6/5/2025 | Approved | JUAN ALVARADO |
| Excavation/Setback/Form/Re-Bar | 6/6/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Deputy Wood Construction | 7/30/2025 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Rough | 8/15/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 8/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Underground Mechanical | 8/15/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 8/20/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 9/3/2025 | Partial Inspection | JUAN ALVARADO |
| Green Building Rough | 9/3/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 9/3/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 9/3/2025 | Approved | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 9/3/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 9/3/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 9/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 9/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 9/16/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 9/16/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 9/18/2025 | Approved | JUAN ALVARADO |
| Insulation | 9/23/2025 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 9/30/2025 | Approved | JUAN ALVARADO |
| Final | 12/5/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 12/5/2025 | Approved | JUAN ALVARADO |
| Green Building Final | 12/5/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 12/5/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 12/5/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 12/22/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 12/22/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Final | 12/22/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 12/22/2025 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 12/22/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 1/5/2026 | Approved | JUAN ALVARADO |
| Final | 1/5/2026 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 1/5/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 1/5/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 1/5/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 2/20/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Service/Power Release | 2/20/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 3/6/2026 | OK to Issue CofO | JUAN ALVARADO |
| Service/Power Release | 3/6/2026 | Approved | JUAN ALVARADO |