1050 N GALLOWAY ST 90272
Certificate Information: 1050 N GALLOWAY ST 90272
- Application / Permit
- 25010-20000-00847
- Plan Check / Job No.
- B25VN04991
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 30' X 73'-11". NFPA 13D SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | RAPHAEL ROSAS |
| Corrections Issued | 3/3/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 3/3/2025 | STEVEN KIM |
| Building Plans Picked Up | 3/4/2025 | APPLICANT |
| Plan Check Approved | 5/16/2025 | RAPHAEL ROSAS |
| Issued | 5/16/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/5/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 3/7/2025 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 3/8/2025 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/8/2025 | Partial Inspection | BOBBY KEY |
| Underground Mechanical | 7/8/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 7/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 7/15/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/17/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/22/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/14/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/24/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 11/26/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 11/26/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 12/3/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 12/3/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/3/2025 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/3/2025 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 12/3/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 12/3/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/8/2025 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/9/2025 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 12/9/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/9/2025 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 12/9/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/10/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 12/24/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 12/31/2025 | Approved | DANIEL VERA |
| Shower Pan | 1/2/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/17/2026 | Approved | TEMISTOCLES CAAL |
| Gas Test | 4/1/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| Underground Mechanical | 4/1/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| Gas Test | 4/29/2026 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 4/29/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 5/11/2026 | Approved | TEMISTOCLES CAAL |