1050 N GALLOWAY ST 90272

Certificate Information: 1050 N GALLOWAY ST 90272

Application / Permit
25010-20000-00847
Plan Check / Job No.
B25VN04991
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 30' X 73'-11". NFPA 13D SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/16/2025
Issuing Office
Valley
Current Status
Issued on 5/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 RAPHAEL ROSAS
Corrections Issued 3/3/2025 RAPHAEL ROSAS
Quality Review Completed 3/3/2025 STEVEN KIM
Building Plans Picked Up 3/4/2025 APPLICANT
Plan Check Approved 5/16/2025 RAPHAEL ROSAS
Issued 5/16/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 3/5/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/6/2025 DARIN LAM
Hydrant and Access approval Cleared 3/7/2025 PATRICK PEREZ
Roof/Waste drainage to street Cleared 3/8/2025 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/8/2025 Partial Inspection BOBBY KEY
Underground Mechanical 7/8/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 7/15/2025 Corrections Issued STEPHANIE SWANSON
Sewer 7/15/2025 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 7/17/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 7/22/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 11/14/2025 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 11/24/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 11/26/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 11/26/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 12/3/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 12/3/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 12/3/2025 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 12/3/2025 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 12/3/2025 Corrections Issued TEMISTOCLES CAAL
Underground Mechanical 12/3/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 12/8/2025 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 12/9/2025 Corrections Issued BOBBY KEY
Green Building Rough 12/9/2025 Approved BOBBY KEY
PLUMBING-Rough 12/9/2025 Approved BOBBY KEY
Verify Sprinkler Sign Off 12/9/2025 Approved BOBBY KEY
PLUMBING-Rough 12/10/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/17/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 12/19/2025 Partial Approval TEMISTOCLES CAAL
Insulation 12/24/2025 Approved DANIEL VERA
Drywall Nailing 12/31/2025 Approved DANIEL VERA
Shower Pan 1/2/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 2/17/2026 Approved TEMISTOCLES CAAL
Gas Test 4/1/2026 No Access for Inspection TEMISTOCLES CAAL
Underground Mechanical 4/1/2026 No Access for Inspection TEMISTOCLES CAAL
Gas Test 4/29/2026 Approved TEMISTOCLES CAAL
Underground Mechanical 4/29/2026 Corrections Issued TEMISTOCLES CAAL
Underground Mechanical 5/11/2026 Approved TEMISTOCLES CAAL