10501-10503 N SHARP AVE 91331
Certificate Information: 10501-10503 N SHARP AVE 91331
- Application / Permit
- 25010-20000-00833
- Plan Check / Job No.
- B25VN04878
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert attached patio cover into an ADU per state law. To be fully sprinklered throughout.
- Permit Issued
- Issued on 7/2/2025
- Issuing Office
- Current Status
- Issued on 7/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2025 | RICARDO RAMIREZ |
| Corrections Issued | 3/3/2025 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 4/9/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 6/26/2025 | ADAM HEGAZI |
| Issued | 7/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/21/2025 | RYAN CASTRO |
| ZA Case | Cleared | 5/21/2025 | MAYELA VILLA |
Contact Information
| Contractor | Os General Construction Inc; Lic. No.: 1108692-B | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 10/6/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/31/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 10/31/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| MERV13>=Rough | 10/31/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| METHANE-Rough | 10/31/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 11/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/12/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Rough | 11/12/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/17/2025 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 11/19/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 12/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 12/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 12/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 12/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/9/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 12/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 12/11/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/12/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/16/2025 | Approved | KEVIN BERBERYAN |
| Pre-Inspection | 12/18/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/2/2026 | Approved | JENNIFER RABUCHIN |
| Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Final | 1/2/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/2/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/2/2026 | Approved | JENNIFER RABUCHIN |