24314 W FRIAR ST 91367
Certificate Information: 24314 W FRIAR ST 91367
- Application / Permit
- 25010-20000-00809
- Plan Check / Job No.
- B25VN04656
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 19'-0" X 29'-8" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
- Permit Issued
- Issued on 4/4/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 3/1/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/5/2025 | APPLICANT |
| Plan Check Approved | 3/12/2025 | YAQUB MIRZA |
| Issued | 4/4/2025 | APPLICANT |
| CofO in Progress | 10/20/2025 | TROY SANDERS |
| Permit Finaled | 10/29/2025 | JOHN JANSON |
| CofO Issued | 10/29/2025 | JOHN JANSON |
| Permit Finaled | 10/29/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 3/4/2025 | SAFA JAVANMARDI |
| Watercourse | Cleared | 3/4/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/11/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Jlemos Builders Inc; Lic. No.: 1098171-B | 4500 PARK GRANADA BLVD STE 202 CALABASAS, CA 91302 |
| Engineer | Shmeit,, Ayman Ivan; Lic. No.: C93325 | 16905 ARMDORE AVE BELLFLOWER, CA 90706 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2025 | Partial Approval | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/18/2025 | Partial Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 4/25/2025 | Corrections Issued | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 5/1/2025 | Approved | GEVORK IPCHYAN |
| Deputy Reinf. Concrete | 5/6/2025 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 6/4/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 7/8/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 7/8/2025 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 7/8/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 7/8/2025 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 7/8/2025 | Approved | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 7/8/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 7/10/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Insulation | 7/15/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 7/21/2025 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/29/2025 | Approved | TROY SANDERS |
| PLUMBING-Final | 9/29/2025 | Approved | TROY SANDERS |
| Final | 10/8/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 10/8/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Final | 10/8/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | GEVORK IPCHYAN |
| Service/Power Release | 10/8/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Smoke Detectors | 10/8/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 10/14/2025 | Corrections Issued | TROY SANDERS |
| Final | 10/20/2025 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 10/20/2025 | Approved | TROY SANDERS |
| HVAC-Final | 10/20/2025 | Approved | TROY SANDERS |
| Service/Power Release | 10/20/2025 | Approved | TROY SANDERS |