11145 W HORTENSE ST 91602

Certificate Information: 11145 W HORTENSE ST 91602

Application / Permit
25010-20000-00789
Plan Check / Job No.
B25VN04478
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE TWO STORY 22'X30'-8" ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(b)(1)].
Permit Issued
Issued on 4/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 DAWN MC NULTY
Corrections Issued 2/24/2025 DAWN MC NULTY
Quality Review Completed 2/25/2025 OMID HEDAYAT
Building Plans Picked Up 2/26/2025 APPLICANT
Applicant returned to address corrections 4/1/2025 DAWN MC NULTY
Plan Check Approved 4/4/2025 DAWN MC NULTY
No Progress 4/4/2025 DAWN MC NULTY
Plan Check Approved 4/4/2025 DAWN MC NULTY
Issued 4/7/2025 APPLICANT
CofO in Progress 1/21/2026 JAVIER RAMOS JR
Permit Finaled 1/29/2026 RUBEN SALAS
Permit Finaled 1/29/2026 RUBEN SALAS
CofO Issued 1/29/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/7/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 3/8/2025 BIAINA HARITUNIAN
CPC Cleared 3/10/2025 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 3/10/2025 CELINA MORENO
Sewer availability Cleared 3/10/2025 CELINA MORENO
Hydrant and Access approval Cleared 3/12/2025 JERRY KAO
Historic monument Cleared 3/14/2025 LAMBERT GIESSINGER

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/21/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/21/2025 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/25/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 4/25/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/13/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Approved JAVIER RAMOS JR
HVAC-Rough 6/5/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/5/2025 Approved JAVIER RAMOS JR
Underground Mechanical 6/5/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/6/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/12/2025 Partial Approval JACK KARGODORIAN
Sewer 6/23/2025 Approved JAVIER RAMOS JR
Underground Mechanical 6/23/2025 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 6/25/2025 Partial Approval JAVIER RAMOS JR
Green Building Rough 6/25/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 6/25/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 6/25/2025 Approved JAVIER RAMOS JR
Insulation 7/1/2025 Approved LOUIS ESCOTO
Drywall Nailing 7/11/2025 Approved LOUIS ESCOTO
Shower Pan 7/11/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 8/4/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 9/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 9/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
MERV13>=Final 9/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/25/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 9/25/2025 Approved JAVIER RAMOS JR
Final 9/25/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/25/2025 Approved JAVIER RAMOS JR
HVAC-Final 9/25/2025 Approved JAVIER RAMOS JR
MERV13>=Final 9/25/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 9/25/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 9/25/2025 Approved JAVIER RAMOS JR
Final 12/23/2025 Corrections Issued JAVIER RAMOS JR
Final 1/21/2026 OK to Issue CofO JAVIER RAMOS JR