13691-13693 W GARBER ST 91331
Certificate Information: 13691-13693 W GARBER ST 91331
- Application / Permit
- 25010-20000-00777
- Plan Check / Job No.
- B25VN04341
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. New SFD (903 sf) per SB9 2nd dwelling unit development CA Gov. Code 65852.21 with attached ADU (903 sf) per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 6/9/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Zoning Architect | 2/27/2025 | RONALD GREENE |
| Assigned to Plan Check Engineer | 3/13/2025 | REZA HAGHIGHAT |
| Corrections Issued | 3/15/2025 | REZA HAGHIGHAT |
| Quality Review Completed | 3/24/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 6/4/2025 | REZA HAGHIGHAT |
| Plan Check Approved | 6/5/2025 | REZA HAGHIGHAT |
| Issued | 6/9/2025 | APPLICANT |
| CofO in Progress | 6/3/2026 | MICHEL ABAJAN |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/7/2025 | ENRIQUE ACOSTA |
| Roof/Waste drainage to street | Cleared | 4/7/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 4/10/2025 | MICHAEL BROWN |
| Senate Bill 9 | Cleared | 4/23/2025 | DAVID URITA |
| Address approval | Cleared | 5/5/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 5/8/2025 | JERRY KAO |
| Zoning Plan Check | Cleared | 5/19/2025 | Ronald Greene |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakobyan,, Sevak; Lic. No.: NA96829 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 7/28/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 7/28/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 7/28/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/5/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/5/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 8/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 8/8/2025 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 11/10/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/19/2025 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Rough | 11/19/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/19/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 11/20/2025 | Conditional Approval | RAUL OLAGI |
| Green Building Rough | 11/20/2025 | Approved | MICHEL ABAJAN |
| Insulation | 11/25/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/2/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/19/2025 | Approved | CHRISTOPHER MORFIN |
| Shower Pan | 12/19/2025 | Approved | CHRISTOPHER MORFIN |
| Sewer | 1/13/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 1/13/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/6/2026 | Approved | MICHEL ABAJAN |
| Final | 5/6/2026 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 5/6/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/6/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 5/6/2026 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/6/2026 | Approved | MICHEL ABAJAN |
| Final | 5/27/2026 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/2/2026 | Approved | MICHEL ABAJAN |
| Final | 6/2/2026 | OK to Issue CofO | MICHEL ABAJAN |