11405 N EL DORADO AVE 91340

Certificate Information: 11405 N EL DORADO AVE 91340

Application / Permit
25010-20000-00768
Plan Check / Job No.
B25VN04306
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 1-story detached ADU per Ordinance (LAMC 12.22 A.33(b)(1)). All work per WFPP
Permit Issued
Issued on 6/23/2025
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/4/2025 HOOMAN HAJIZADEH
Corrections Issued 3/5/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 6/3/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 6/5/2025 AMY GUEVARRA
Plan Check Approved 6/12/2025 AMY GUEVARRA
Issued 6/23/2025 APPLICANT
CofO in Progress 6/26/2026 JENNIFER RABUCHIN
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/16/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 3/16/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 3/25/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/25/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/5/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/5/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 12/5/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/15/2025 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/15/2025 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 12/15/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/23/2025 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 12/23/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 12/23/2025 Approved JENNIFER RABUCHIN
Green Building Rough 12/23/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/23/2025 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/23/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/9/2026 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/9/2026 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/20/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/20/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/20/2026 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 1/20/2026 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 1/20/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/2/2026 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 2/2/2026 Approved MATTHEW NELSON
Green Building Rough 2/2/2026 Approved MATTHEW NELSON
HVAC-Rough 2/2/2026 Approved MATTHEW NELSON
Shower Pan 2/2/2026 Approved MATTHEW NELSON
Wood Frame 2/2/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/6/2026 Partial Approval JENNIFER RABUCHIN
Insulation 2/11/2026 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 2/11/2026 Partial Approval JENNIFER RABUCHIN
Insulation 2/17/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/20/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/9/2026 Approved MICHEL ABAJAN
Gas Test 4/9/2026 Approved MICHEL ABAJAN
HVAC-Final 4/9/2026 Approved MICHEL ABAJAN
PLUMBING-Final 4/9/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/29/2026 Approved JENNIFER RABUCHIN
Final 5/29/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/29/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 5/29/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/29/2026 Approved JENNIFER RABUCHIN
Final 6/23/2026 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 6/23/2026 Approved JENNIFER RABUCHIN