7414 N CLAIRE AVE 91335
Certificate Information: 7414 N CLAIRE AVE 91335
- Application / Permit
- 25010-20000-00764
- Plan Check / Job No.
- B25VN04281
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- Current Status
- Issued on 11/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2025 | MADISON ODELL |
| Corrections Issued | 2/25/2025 | MADISON ODELL |
| Applicant returned to address corrections | 11/6/2025 | MINA HABILI |
| Plan Check Approved | 11/20/2025 | NAREG ATARIAN |
| Issued | 11/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/26/2025 | CARLOS AGUILERA |
| Private sewage disp. approval | Cleared | 11/18/2025 | MICHAEL TEMPLE |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | C I D Builders And Developers Inc; Lic. No.: 958193-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/12/2025 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/23/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 1/9/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 1/9/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/9/2026 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/2/2026 | Conditional Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 2/2/2026 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 2/2/2026 | Approved | ARUTYUN MADATYAN |
| Insulation | 2/5/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 2/5/2026 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 2/11/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/17/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/26/2026 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 3/26/2026 | Approved | JEFFREY HARTLINE |
| Sewer | 4/2/2026 | Not Ready for Inspection | GEVORK IPCHYAN |