7828 N SHOSHONE AVE 91325

Certificate Information: 7828 N SHOSHONE AVE 91325

Application / Permit
25010-20000-00755
Plan Check / Job No.
B25VN04246
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR SHAPED 29'-2" X 34'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC12.22A.33(b)(1)
Permit Issued
Issued on 3/26/2025
Issuing Office
Current Status
CofO in Progress on 5/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/19/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 DANIEL ABRAMYAN
Corrections Issued 2/24/2025 DANIEL ABRAMYAN
Quality Review Completed 2/25/2025 OMID HEDAYAT
Building Plans Picked Up 2/26/2025 APPLICANT
Applicant returned to address corrections 3/14/2025 DANIEL ABRAMYAN
Plan Check Approved 3/26/2025 DANIEL ABRAMYAN
Issued 3/26/2025 APPLICANT
CofO in Progress 5/12/2026 MICHAEL CORTEZ

Permit Application Clearance Information

Address approval Cleared 2/24/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 2/24/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/25/2025 RYAN CASTRO
Sewer availability Cleared 2/25/2025 RYAN CASTRO
Construction near power lines Cleared 3/7/2025 WALTER RAMIREZ
Construction within easement Cleared 3/7/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/3/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 6/5/2025 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 6/5/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 6/16/2025 Approved SALVADOR MARTINEZ
Pre-Inspection 8/20/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 9/10/2025 Approved MICHEL ABAJAN
HVAC-Rough 9/10/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Partial Approval WAYNE REGESTER
PLUMBING-Rough 9/26/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Approved GAREN HAYRAPETYAN
Shower Pan 10/3/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 10/3/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/16/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/13/2025 Approved WAYNE REGESTER
Green Building Rough 11/13/2025 Approved WAYNE REGESTER
Insulation 11/13/2025 Approved WAYNE REGESTER
Verify Sprinkler Sign Off 11/13/2025 Approved WAYNE REGESTER
Drywall Nailing 11/24/2025 Approved GAREN HAYRAPETYAN
Gas Test 4/17/2026 Approved KIRK SANDERS
ELECTRICAL-Final 5/6/2026 Corrections Issued KIRK SANDERS
HVAC-Final 5/6/2026 Corrections Issued KIRK SANDERS
PLUMBING-Final 5/6/2026 Corrections Issued KIRK SANDERS
Final 5/11/2026 OK to Issue CofO MICHAEL CORTEZ
Green Building Final 5/11/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Not Required MICHAEL CORTEZ
Service/Power Release 5/11/2026 Approved MICHAEL CORTEZ
Smoke Detectors 5/11/2026 Approved MICHAEL CORTEZ