7420-7422 N ROYER AVE 91307

Certificate Information: 7420-7422 N ROYER AVE 91307

Application / Permit
25010-20000-00742
Plan Check / Job No.
B25VN04199
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: CONVERT (351 SF) PORTION OF THE (E) SINGLE FAMILY DWELLING INTO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) and 66333.
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 PINANK PATEL
Corrections Issued 2/21/2025 PINANK PATEL
Applicant returned to address corrections 5/30/2025 SARKIS HARABEDIAN
Applicant returned to address corrections 6/4/2025 GURUNATH NESARAJAH
Applicant returned to address corrections 6/18/2025 ISIS ARGUETA
Plan Check Approved 6/24/2025 ISIS ARGUETA
Issued 6/25/2025 APPLICANT
CofO in Progress 5/19/2026 JEFFREY HARTLINE
Permit Finaled 5/21/2026 JOHN JANSON
CofO Issued 5/21/2026 JOHN JANSON
Permit Finaled 5/21/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/24/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/24/2025 CARLOS AGUILERA
Sewer availability Cleared 2/24/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/12/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 12/12/2025 Not Ready for Inspection JEFFREY HARTLINE
Pre-Inspection 12/12/2025 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 12/12/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 5/8/2026 Corrections Issued JEFFREY HARTLINE
Gas Test 5/8/2026 Approved JEFFREY HARTLINE
Smoke Detectors 5/8/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 5/15/2026 Approved JEFFREY HARTLINE
Final 5/15/2026 OK to Issue CofO JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved JEFFREY HARTLINE