1121 N EMBURY ST 90272
Certificate Information: 1121 N EMBURY ST 90272
- Application / Permit
- 25010-20000-00736
- Plan Check / Job No.
- B25VN04156
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE **2025 Wildfire Project *** FIRE REBUILD _ PACIFIC PALISADES*** Rebuild SFD like for like based on approved plans, property CofO'd 2024
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Current Status
- Issued on 4/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2025 | SARKIS HARABEDIAN |
| Corrections Issued | 2/18/2025 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 2/20/2025 | APPLICANT |
| Plan Check Approved | 3/25/2025 | SARKIS HARABEDIAN |
| Issued | 4/11/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/20/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/20/2025 | HISASHI KOBAYAKAWA |
| Public Works-Highway Ded. | Cleared | 2/20/2025 | HISASHI KOBAYAKAWA |
| Public Works-Open Permits | Cleared | 2/20/2025 | HISASHI KOBAYAKAWA |
| Public Works-Sewers | Cleared | 2/20/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 3/3/2025 | RUEL COLE |
Contact Information
| Contractor | Ortam Construction Inc; Lic. No.: 880225-B | 4500 PARK GRANADA #202 CALABASAS, CA 91302 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 5/13/2025 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/16/2025 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/23/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 5/23/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 6/30/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 7/18/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 8/8/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/26/2025 | Approved | KENNETH NAGLE |
| HVAC-Rough | 8/26/2025 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Partial Approval | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 8/27/2025 | Approved | MICHAEL ALLEN |
| Deputy Wood Construction | 8/28/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 9/8/2025 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 9/12/2025 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 9/12/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 9/17/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/17/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/9/2026 | Not Ready for Inspection | DANIEL VERA |
| Pre-Inspection | 5/27/2026 | Partial Inspection | TEMISTOCLES CAAL |