21810 W INGOMAR ST 91304
Certificate Information: 21810 W INGOMAR ST 91304
- Application / Permit
- 25010-20000-00726
- Plan Check / Job No.
- B25VN04117
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- Current Status
- CofO Issued on 12/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | MADISON ODELL |
| Corrections Issued | 2/22/2025 | MADISON ODELL |
| Applicant returned to address corrections | 4/2/2025 | MADISON ODELL |
| Applicant returned to address corrections | 4/10/2025 | MADISON ODELL |
| Plan Check Approved | 4/15/2025 | MADISON O'DELL |
| Issued | 5/13/2025 | APPLICANT |
| CofO in Progress | 9/25/2025 | ALEXANDER HANDY |
| Permit Finaled | 12/15/2025 | JOHN JANSON |
| CofO Issued | 12/15/2025 | JOHN JANSON |
| Permit Finaled | 12/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Tract Map conditions | Cleared | 3/1/2025 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/26/2025 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 3/27/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Sharp Builders & Son; Lic. No.: 1058253-B | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2025 | Partial Approval | SCOTT SOBEL |
| Sewer | 6/2/2025 | Approved | SCOTT SOBEL |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/5/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 7/7/2025 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 7/7/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 7/7/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/10/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 7/10/2025 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 7/10/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/15/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 7/15/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 7/23/2025 | Approved | ALEXANDER HANDY |
| Final | 9/22/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 9/22/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 9/22/2025 | Not Required | ALEXANDER HANDY |
| Smoke Detectors | 9/22/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/23/2025 | Approved | ALEXANDER HANDY |
| Final | 9/23/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 9/23/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/23/2025 | Approved | ALEXANDER HANDY |