6736 N GENTRY AVE 91606

Certificate Information: 6736 N GENTRY AVE 91606

Application / Permit
25010-20000-00725
Plan Check / Job No.
B25VN04114
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER GCS 66323(a)(4) NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/28/2025
Issuing Office
Current Status
CofO in Progress on 4/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 ALEC MOUSAKHANIAN
Corrections Issued 2/25/2025 ALEC MOUSAKHANIAN
Plan Check Approved 4/8/2025 ALEC MOUSAKHANIAN
Issued 4/28/2025 APPLICANT
CofO in Progress 4/14/2026 ROBERTO PALACIOS-LOPEZ

Permit Application Clearance Information

Address approval Cleared 2/24/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 2/24/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 3/15/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/19/2025 CARLOS AGUILERA
Construction near power lines Cleared 4/1/2025 GEVORK KARAPETYAN

Contact Information

Contractor Express Construction Group Inc; Lic. No.: 625249-B       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/28/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/2/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/27/2025 Approved JOSE AVILA
PLUMBING-Rough 10/28/2025 Approved JOSE AVILA
PLUMBING-Rough 10/29/2025 Approved JOSE AVILA
HVAC-Rough 10/30/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 11/7/2025 Partial Inspection JOSE AVILA
HVAC-Rough 11/7/2025 Approved JOSE AVILA
Drywall Nailing 11/19/2025 Approved JOSE AVILA
Insulation 11/19/2025 Approved JOSE AVILA
Shower Pan 11/25/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 4/8/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 4/8/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/8/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/8/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/8/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/8/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/8/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/8/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 4/13/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/13/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 4/13/2026 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/13/2026 Approved ROBERTO PALACIOS-LOPEZ