17423 W LOS ALIMOS ST 91344

Certificate Information: 17423 W LOS ALIMOS ST 91344

Application / Permit
25010-20000-00722
Plan Check / Job No.
B25VN04095
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New detached ADU per GC 66323(a)(2)
Permit Issued
Issued on 6/26/2025
Issuing Office
Current Status
CofO Issued on 12/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2025 APPLICANT
Assigned to Plan Check Engineer 2/25/2025 AMY GUEVARRA
Corrections Issued 3/6/2025 AMY GUEVARRA
Applicant returned to address corrections 3/13/2025 AMY GUEVARRA
Applicant returned to address corrections 3/20/2025 AMY GUEVARRA
Plan Check Approved 4/5/2025 REZA HAGHIGHAT
Issued 6/26/2025 APPLICANT
CofO in Progress 11/18/2025 STEVEN BACK
CofO in Progress 11/21/2025 STEVEN BACK
CofO in Progress 11/21/2025 STEVEN BACK
Permit Finaled 12/1/2025 JOHN JANSON
CofO Issued 12/1/2025 JOHN JANSON
Permit Finaled 12/1/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/8/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/8/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/8/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/10/2025 LEE GUILBEAUX
Sewer availability Cleared 3/10/2025 LEE GUILBEAUX

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/22/2025 Partial Approval STEVEN BACK
Pre-Inspection 7/22/2025 Not Ready for Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/25/2025 Approved STEVEN BACK
Footing/Foundation/Slab 7/25/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Partial Approval STEVEN BACK
Deputy Wood Construction 8/18/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Approved STEVEN BACK
PLUMBING-Rough 8/18/2025 Approved STEVEN BACK
Interior/Exterior Lathing 8/21/2025 Partial Approval STEVEN BACK
ELECTRICAL-Rough 8/29/2025 Not Ready for Inspection STEVEN BACK
HVAC-Rough 8/29/2025 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 9/2/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 9/2/2025 Approved GEVORK IPCHYAN
Green Building Rough 9/2/2025 Approved GEVORK IPCHYAN
HVAC-Rough 9/2/2025 Approved GEVORK IPCHYAN
Insulation 9/5/2025 Conditional Approval CHRIS CHRISTENSEN
Shower Pan 9/5/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 9/11/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/16/2025 Approved JEFFREY PARD
Final 10/31/2025 Corrections Issued STEVEN BACK
Green Building Final 10/31/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Not Ready STEVEN BACK
Smoke Detectors 10/31/2025 Approved STEVEN BACK
Final 11/18/2025 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Approved STEVEN BACK
Service/Power Release 11/18/2025 Approved STEVEN BACK