17423 W LOS ALIMOS ST 91344
Certificate Information: 17423 W LOS ALIMOS ST 91344
- Application / Permit
- 25010-20000-00722
- Plan Check / Job No.
- B25VN04095
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New detached ADU per GC 66323(a)(2)
- Permit Issued
- Issued on 6/26/2025
- Issuing Office
- Current Status
- CofO Issued on 12/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2025 | AMY GUEVARRA |
| Corrections Issued | 3/6/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/13/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/20/2025 | AMY GUEVARRA |
| Plan Check Approved | 4/5/2025 | REZA HAGHIGHAT |
| Issued | 6/26/2025 | APPLICANT |
| CofO in Progress | 11/18/2025 | STEVEN BACK |
| CofO in Progress | 11/21/2025 | STEVEN BACK |
| CofO in Progress | 11/21/2025 | STEVEN BACK |
| Permit Finaled | 12/1/2025 | JOHN JANSON |
| CofO Issued | 12/1/2025 | JOHN JANSON |
| Permit Finaled | 12/1/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/8/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/8/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/10/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Adu Rc Builders; Lic. No.: 1080967-B | , |
| Contractor | Ca Construction Group Inc; Lic. No.: 1080967-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/22/2025 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 7/22/2025 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 7/25/2025 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/25/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 8/18/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/18/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/21/2025 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 8/29/2025 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 8/29/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 9/2/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 9/2/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 9/2/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 9/5/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Shower Pan | 9/5/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/11/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 9/16/2025 | Approved | JEFFREY PARD |
| Final | 10/31/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/31/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 10/31/2025 | Approved | STEVEN BACK |
| Final | 11/18/2025 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 11/18/2025 | Approved | STEVEN BACK |