16659 W ADLON ROAD 91436

Certificate Information: 16659 W ADLON ROAD 91436

Application / Permit
25010-20000-00716
Plan Check / Job No.
B25VN04055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 41' X 21' ONE STORY DETACHED ACCESORY DWELLING UNIT AS PER GC 66323(a)(1) WITH 52'4" X 44'4" ATTACHED OPEN TRELLIS, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
Issued on 4/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 RARES BODEA
Corrections Issued 2/27/2025 RARES BODEA
Quality Review Completed 3/3/2025 STEVEN KIM
Applicant returned to address corrections 3/27/2025 RARES BODEA
Plan Check Approved 4/8/2025 RARES BODEA
Issued 4/8/2025 APPLICANT
Building Plans Picked Up 4/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/27/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 2/27/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/27/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/27/2025 EDGAR ALCARAZ
Sewer availability Cleared 2/27/2025 EDGAR ALCARAZ
Construction near power lines Cleared 2/28/2025 WALTER RAMIREZ
Distance to fire station Cleared 3/5/2025 LAVEON RIDER
Hydrant and Access approval Cleared 3/5/2025 LAVEON RIDER
GPI Written Notices Cleared 4/8/2025 RARES BODEA
Grading Pre-Inspection Cleared 4/8/2025 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/4/2025 Partial Approval JOHN KIDWELL
Underground Mechanical 8/7/2025 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/22/2025 Conditional Approval JOHN KIDWELL
Deputy Drilled-In Anchors 3/2/2026 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/2/2026 Conditional Approval JOHN KIDWELL
Footing/Foundation/Slab 3/2/2026 Conditional Approval JOHN KIDWELL
ELECTRICAL-Rough 3/9/2026 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Partial Approval SEAN WIRCH
HVAC-Rough 3/9/2026 Approved SEAN WIRCH
PLUMBING-Rough 3/9/2026 Approved SEAN WIRCH
BUILDING-Rough-Frame 3/25/2026 Corrections Issued THOMAS FINNILA
Green Building Rough 3/25/2026 Corrections Issued THOMAS FINNILA
Verify Sprinkler Sign Off 3/25/2026 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 4/6/2026 Approved THOMAS FINNILA
Green Building Rough 4/6/2026 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/6/2026 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 4/6/2026 Approved THOMAS FINNILA
Insulation 4/20/2026 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/20/2026 Partial Approval JOHN KIDWELL
Shower Pan 4/20/2026 Approved JOHN KIDWELL
Underground Mechanical 4/20/2026 Partial Approval JOHN KIDWELL
Drywall Nailing 5/4/2026 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/4/2026 Partial Approval JOHN KIDWELL