12339 W SHELDON ST 91352
Certificate Information: 12339 W SHELDON ST 91352
- Application / Permit
- 25010-20000-00706
- Plan Check / Job No.
- B25VN03994
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY SFD PER SB9 PER WFPP (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/11/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/11/2025 | JASON HEALEY |
| Building Plans Picked Up | 3/12/2025 | APPLICANT |
| Plan Check Approved | 5/20/2025 | NILOOFAR MEHRAIN |
| Issued | 5/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/18/2025 | PATRICK PEREZ |
| Public Works-Highway Ded. | Cleared | 3/18/2025 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 3/27/2025 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/27/2025 | LEE GUILBEAUX |
| Senate Bill 9 | Cleared | 4/24/2025 | FIPE LEILUA |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/27/2025 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 5/19/2025 | MIGUEL CRISOSTOMO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/3/2025 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/3/2025 | Partial Inspection | MATTHEW NELSON |
| Pre-Inspection | 9/3/2025 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Final | 10/1/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/17/2025 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 11/6/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 11/6/2025 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 11/6/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 11/6/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 11/6/2025 | Partial Approval | MATTHEW NELSON |
| Gas Test | 12/2/2025 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 12/2/2025 | Approved | MATTHEW NELSON |
| Sewer | 12/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/9/2026 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 1/9/2026 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 1/9/2026 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 1/9/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/22/2026 | Partial Approval | MATTHEW NELSON |
| Insulation | 1/29/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/6/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/13/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/21/2026 | Approved | WAYNE REGESTER |