11014-11014 1/2 W OXNARD ST 91606

Certificate Information: 11014-11014 1/2 W OXNARD ST 91606

Application / Permit
25010-20000-00688
Plan Check / Job No.
B25VN03915
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW 38'-4" X 28'-1" TWO STORY BUILDING (ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) ON FIRST FLOOR; DWELLING UNIT ON SECOND FLOOR); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/27/2025
Issuing Office
Valley
Current Status
Issued on 3/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/14/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 SELLA BENYAMIN
Corrections Issued 2/27/2025 SELLA BENYAMIN
Quality Review Completed 3/6/2025 STEVEN KIM
Plan Check Approved 3/18/2025 SELLA BENYAMIN
No Progress 3/23/2025 SELLA BENYAMIN
Plan Check Approved 3/23/2025 SELLA BENYAMIN
Issued 3/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/28/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/28/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 2/28/2025 RYAN CASTRO
Sewer availability Cleared 2/28/2025 RYAN CASTRO
Hydrant and Access approval Cleared 3/17/2025 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/22/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 4/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/25/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Partial Approval JACK KARGODORIAN
Green Building Rough 5/28/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/28/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 7/30/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/5/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 8/5/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 8/13/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 8/14/2025 Approved JOSE AVILA
Drywall Nailing 8/19/2025 Approved JOSE AVILA
Interior/Exterior Lathing 8/19/2025 Approved JOSE AVILA
Final 1/15/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 1/15/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/15/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/15/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/15/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 1/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 1/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/23/2026 Approved ROBERTO PALACIOS-LOPEZ