11014-11014 1/2 W OXNARD ST 91606
Certificate Information: 11014-11014 1/2 W OXNARD ST 91606
- Application / Permit
- 25010-20000-00688
- Plan Check / Job No.
- B25VN03915
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 38'-4" X 28'-1" TWO STORY BUILDING (ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) ON FIRST FLOOR; DWELLING UNIT ON SECOND FLOOR); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Valley
- Current Status
- Issued on 3/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | SELLA BENYAMIN |
| Corrections Issued | 2/27/2025 | SELLA BENYAMIN |
| Quality Review Completed | 3/6/2025 | STEVEN KIM |
| Plan Check Approved | 3/18/2025 | SELLA BENYAMIN |
| No Progress | 3/23/2025 | SELLA BENYAMIN |
| Plan Check Approved | 3/23/2025 | SELLA BENYAMIN |
| Issued | 3/27/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/28/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 2/28/2025 | RYAN CASTRO |
| Hydrant and Access approval | Cleared | 3/17/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/22/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 5/28/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/28/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 7/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/5/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 8/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 8/13/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 8/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/14/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 8/19/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/19/2025 | Approved | JOSE AVILA |
| Final | 1/15/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 1/15/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/15/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 1/15/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 1/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 1/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 1/23/2026 | Approved | ROBERTO PALACIOS-LOPEZ |