843 N HARTZELL ST 90272

Certificate Information: 843 N HARTZELL ST 90272

Application / Permit
25010-20000-00682
Plan Check / Job No.
B25VN03867
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/18/2025
Issuing Office
Valley
Current Status
Issued on 4/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 JEROME MAGAT PALMA
Corrections Issued 2/13/2025 JEROME MAGAT PALMA
Building Plans Picked Up 2/18/2025 APPLICANT
Applicant returned to address corrections 3/5/2025 JEROME MAGAT PALMA
Plan Check Approved 3/6/2025 JEROME MAGAT PALMA
No Progress 3/7/2025 JEROME MAGAT PALMA
Issued 4/18/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/25/2025 DARIN LAM
Sewer availability Cleared 2/25/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/26/2025 DARIN LAM
Hydrant and Access approval Cleared 3/3/2025 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Smith, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Wang, Hongyu; Lic. No.: C72679 10530 HOPE MILLS DR      LAS VEGAS, NV 89135

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/13/2025 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/16/2025 No Access for Inspection MEL KHACHATOURIAN
Pre-Inspection 5/21/2025 Partial Inspection TEMISTOCLES CAAL
PLUMBING-Rough 5/22/2025 Conditional Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/23/2025 Partial Approval DANIEL VERA
Footing/Foundation/Slab 6/2/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Corrections Issued BOBBY KEY
Deputy Wood Construction 7/3/2025 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 8/7/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 8/7/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/3/2025 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 9/11/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 9/12/2025 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 9/12/2025 Approved MEL KHACHATOURIAN
Green Building Rough 9/12/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 9/12/2025 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 9/12/2025 Approved MEL KHACHATOURIAN
Insulation 10/1/2025 Corrections Issued TEMISTOCLES CAAL
Drywall Nailing 10/8/2025 Conditional Approval TEMISTOCLES CAAL
Insulation 10/8/2025 Conditional Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 12/29/2025 Approved DANIEL VERA
Shower Pan 12/29/2025 Corrections Issued DANIEL VERA
Shower Pan 12/30/2025 Approved DANIEL VERA
Drywall Nailing 1/21/2026 Approved TEMISTOCLES CAAL
Insulation 1/21/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/21/2026 Approved TEMISTOCLES CAAL
Underground Mechanical 4/20/2026 Corrections Issued DANIEL VERA
Underground Mechanical 4/21/2026 Not Ready for Inspection DANIEL VERA
Gas Test 4/23/2026 Approved MICHAEL ALLEN
Underground Mechanical 4/23/2026 Approved MICHAEL ALLEN