875-877 E 47TH ST 90011
Certificate Information: 875-877 E 47TH ST 90011
- Application / Permit
- 25010-20000-00677
- Plan Check / Job No.
- B25VN03859
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE NFPA13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2025 | JAD BASMA |
| Corrections Issued | 2/17/2025 | JAD BASMA |
| Quality Review Completed | 2/18/2025 | PRANITA SHAH |
| Plan Check Approved | 5/15/2025 | JAD BASMA |
| No Progress | 5/15/2025 | JAD BASMA |
| Plan Check Approved | 5/15/2025 | JAD BASMA |
| Issued | 6/4/2025 | APPLICANT |
| CofO in Progress | 2/2/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/5/2026 | DEROLD HAUFF |
| CofO Issued | 2/5/2026 | DEROLD HAUFF |
| Permit Finaled | 2/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/3/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 3/6/2025 | JERRY KAO |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | CELINA MORENO |
| Permit | Cleared | 3/11/2025 | CELINA MORENO |
| Sewer availability | Cleared | 3/19/2025 | CELINA MORENO |
| Trees in Parkway | Cleared | 3/25/2025 | BRANDON WONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/26/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/31/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 10/31/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 11/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 11/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/10/2025 | Conditional Approval | MICHAEL LEWIS |
| Insulation | 11/10/2025 | Approved | MICHAEL LEWIS |
| Green Building Rough | 11/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/17/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/18/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/27/2026 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 1/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/27/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/27/2026 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/27/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/28/2026 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 1/28/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/28/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/29/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/29/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/29/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/2/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/2/2026 | Approved | ALEJANDRO DE ARTOLA |