10576 N ANDASOL AVE 91344
Certificate Information: 10576 N ANDASOL AVE 91344
- Application / Permit
- 25010-20000-00670
- Plan Check / Job No.
- B25VN01441
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 33'-11" X 24'-3" NEW DETACHED ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Current Status
- CofO Issued on 6/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | SELLA BENYAMIN |
| Corrections Issued | 2/13/2025 | SELLA BENYAMIN |
| Quality Review Completed | 2/20/2025 | STEVEN KIM |
| Applicant returned to address corrections | 3/11/2025 | SELLA BENYAMIN |
| Plan Check Approved | 3/27/2025 | SELLA BENYAMIN |
| No Progress | 3/27/2025 | SELLA BENYAMIN |
| Plan Check Approved | 3/27/2025 | SELLA BENYAMIN |
| Plan Check Approved | 5/6/2025 | SELLA BENYAMIN |
| Issued | 6/20/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | KEVIN BERBERYAN |
| CofO Issued | 6/11/2026 | RUBEN SALAS |
| Permit Finaled | 6/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/25/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/13/2025 | BIAINA HARITUNIAN |
| ZI | Cleared | 3/13/2025 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/13/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Sewer | 8/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 8/21/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/21/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/21/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/7/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/7/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/7/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/13/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 12/2/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/2/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 12/10/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/24/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/24/2025 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 1/22/2026 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/6/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/6/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 5/6/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/6/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 5/6/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 5/6/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/6/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 5/6/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/6/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 5/15/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 5/15/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 5/21/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 5/21/2026 | Not Ready for Inspection | KEVIN BERBERYAN |