10576 N ANDASOL AVE 91344

Certificate Information: 10576 N ANDASOL AVE 91344

Application / Permit
25010-20000-00670
Plan Check / Job No.
B25VN01441
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 33'-11" X 24'-3" NEW DETACHED ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 6/20/2025
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 SELLA BENYAMIN
Corrections Issued 2/13/2025 SELLA BENYAMIN
Quality Review Completed 2/20/2025 STEVEN KIM
Applicant returned to address corrections 3/11/2025 SELLA BENYAMIN
Plan Check Approved 3/27/2025 SELLA BENYAMIN
No Progress 3/27/2025 SELLA BENYAMIN
Plan Check Approved 3/27/2025 SELLA BENYAMIN
Plan Check Approved 5/6/2025 SELLA BENYAMIN
Issued 6/20/2025 APPLICANT
CofO in Progress 5/21/2026 KEVIN BERBERYAN
CofO Issued 6/11/2026 RUBEN SALAS
Permit Finaled 6/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/25/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/25/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/25/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/13/2025 BIAINA HARITUNIAN
ZI Cleared 3/13/2025 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/13/2025 Partial Approval NICHOLAS TROWBRIDGE
Sewer 8/13/2025 Approved NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 8/21/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 8/25/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 10/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/7/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 11/7/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 11/7/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/7/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/13/2025 Approved CHRISTOPHER ROJAS
Insulation 12/2/2025 Approved JOSE AVILA
Interior/Exterior Lathing 12/2/2025 Approved JOSE AVILA
Drywall Nailing 12/10/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/24/2025 Approved CHRISTOPHER ROJAS
Shower Pan 12/24/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 1/22/2026 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/6/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/6/2026 Corrections Issued CHRISTOPHER ROJAS
Final 5/6/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/6/2026 Approved CHRISTOPHER ROJAS
Green Building Final 5/6/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 5/6/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 5/6/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 5/6/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 5/6/2026 Approved CHRISTOPHER ROJAS
Final 5/15/2026 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 5/15/2026 Not Ready for Inspection KEVIN BERBERYAN
Final 5/21/2026 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 5/21/2026 Not Ready for Inspection KEVIN BERBERYAN