15713 W ROSCOE BLVD 91343
Certificate Information: 15713 W ROSCOE BLVD 91343
- Application / Permit
- 25010-20000-00654
- Plan Check / Job No.
- B25VN03724
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- *eplan* Project Homekey, construction of a new multi-purpose building (as an accessory use) to support an interim housing project. Phase II.
- Permit Issued
- Issued on 9/12/2025
- Issuing Office
- Current Status
- Issued on 9/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/14/2025 | APPLICANT |
| Assigned to Zoning Architect | 2/20/2025 | LY CHEA |
| Assigned to Plan Check Engineer | 2/27/2025 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/3/2025 | SALVADOR QUINTANILLA |
| Quality Review Completed | 3/5/2025 | PETER KIM |
| Applicant returned to address corrections | 5/1/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 5/9/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/5/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/6/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/10/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 9/11/2025 | SALVADOR QUINTANILLA |
| Issued | 9/12/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/6/2025 | MAYELA VILLA |
| Miscellaneous | Cleared | 3/6/2025 | MAYELA VILLA |
| ZA Case | Cleared | 3/6/2025 | MAYELA VILLA |
| ZA Case | Cleared | 3/6/2025 | MAYELA VILLA |
| Highway dedication | Cleared | 3/29/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2025 | CARLOS AGUILERA |
| Public Housing | Cleared | 4/7/2025 | JOEL LAUNCHBAUGH |
| Miscellaneous | Cleared | 4/9/2025 | DANIEL CORONADO |
| Sewer availability | Cleared | 5/6/2025 | CARLOS AGUILERA |
| Green Code | Cleared | 6/17/2025 | MICHAEL AYERS |
| Address approval | Cleared | 7/25/2025 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 8/13/2025 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 8/20/2025 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 8/20/2025 | LEE GUILBEAUX |
| Fire Marshal Fire Life Safety | Cleared | 8/28/2025 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 9/2/2025 | Minye Pak |
| Zoning Plan Check | Cleared | 9/5/2025 | Minye Pak |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Buckley,, Jonathan Kaino; Lic. No.: S6407 | 8910 UNIVERSITY CENTER LANE SUITE 400 SAN DIEGO, CA 92122 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 9/29/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 9/29/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Partial Inspection | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 12/18/2025 | Off-Hour Fees Due | |
| Deputy Other (see comments) | 2/13/2026 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 2/13/2026 | Conditional Approval | JEFFREY DURAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 2/23/2026 | Partial Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 2/23/2026 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 2/23/2026 | Partial Approval | GREGORY POMISH |
| Deputy Drilled-In Anchors | 2/27/2026 | Approved | JOHN KITCKO |
| Insulation | 3/5/2026 | Approved | GREGORY POMISH |
| Green Building Rough | 3/6/2026 | Partial Inspection | GREGORY POMISH |
| Insulation | 3/6/2026 | Partial Approval | GREGORY POMISH |
| Structural Steel Frame | 3/6/2026 | Not Ready for Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 3/6/2026 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 3/6/2026 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 3/10/2026 | Partial Approval | GREGORY POMISH |
| Insulation | 3/10/2026 | Partial Approval | GREGORY POMISH |
| Structural Steel Frame | 3/12/2026 | Partial Inspection | GREGORY POMISH |
| Drywall Nailing | 3/18/2026 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 3/18/2026 | Partial Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 3/31/2026 | Approved | EDWIN GREGORYONA |
| Insulation | 5/28/2026 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 5/28/2026 | Partial Inspection | EDWIN GREGORYONA |
| Insulation | 6/1/2026 | Partial Approval | EDWIN GREGORYONA |