12116 N BRADFORD PL 91344

Certificate Information: 12116 N BRADFORD PL 91344

Application / Permit
25010-20000-00646
Plan Check / Job No.
B24VN27407
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
New recreation room with 10-foot x 14-foot footprint
Permit Issued
Issued on 7/18/2025
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2025 APPLICANT
Assigned to Plan Check Engineer 2/19/2025 SUNMIN LEE
Corrections Issued 2/20/2025 SUNMIN LEE
Applicant returned to address corrections 4/28/2025 SUNMIN LEE
Applicant returned to address corrections 5/6/2025 SUNMIN LEE
Plan Check Approved 6/5/2025 SUNMIN LEE
Issued 7/18/2025 APPLICANT
CofO in Progress 2/19/2026 JEFFREY PARD
Permit Finaled 2/23/2026 JOHN JANSON
CofO Issued 2/23/2026 JOHN JANSON
Permit Finaled 2/23/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/3/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/3/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 3/4/2025 SAFA JAVANMARDI
Construction within easement Cleared 3/17/2025 ENRIQUE ACOSTA
Hydrant and Access approval Cleared 4/7/2025 KENNETH FRASER
Grading Pre-Inspection Cleared 5/1/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Sparks,, David Michael; Lic. No.: C65739 2996 SLY FOX CIRCLE      ELIZABETH, CO 80107

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2025 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 11/7/2025 Approved KRISTEN CAUSEY
Deputy Reinf. Concrete 11/10/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 11/20/2025 Approved STEVEN BACK
ELECTRICAL-Rough 11/20/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Approved STEVEN BACK
Green Building Rough 11/20/2025 Approved STEVEN BACK
Interior/Exterior Lathing 11/20/2025 Approved STEVEN BACK
Verify Sprinkler Sign Off 11/20/2025 Approved STEVEN BACK
Drywall Nailing 11/24/2025 Approved STEVEN BACK
Insulation 11/24/2025 Approved STEVEN BACK
Drywall Nailing 11/25/2025 Approved STEVEN BACK
Final 1/14/2026 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 1/14/2026 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Approved STEVEN BACK
Service/Power Release 1/14/2026 Not Required STEVEN BACK
Smoke Detectors 1/14/2026 Approved STEVEN BACK
ELECTRICAL-Final 1/16/2026 Corrections Issued STEVEN BACK
ELECTRICAL-Final 1/28/2026 Approved STEVEN BACK
Final 1/28/2026 Corrections Issued STEVEN BACK
HVAC-Final 1/28/2026 Not Ready for Inspection STEVEN BACK
Final 2/10/2026 Not Ready for Inspection JEFFREY PARD
HVAC-Final 2/10/2026 Not Ready for Inspection JEFFREY PARD
Final 2/12/2026 OK to Issue CofO JEFFREY PARD
HVAC-Final 2/12/2026 Approved JEFFREY PARD