16304 W LOS ALIMOS ST 91344
Certificate Information: 16304 W LOS ALIMOS ST 91344
- Application / Permit
- 25010-20000-00617
- Plan Check / Job No.
- B25VN03450
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. New 2-story detached Accessory Dwelling Unit per LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 12/1/2025
- Issuing Office
- Current Status
- Issued on 12/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | ALEXANDER JOO |
| Corrections Issued | 2/28/2025 | ALEXANDER JOO |
| Quality Review Completed | 2/28/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 4/22/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 7/18/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 7/22/2025 | ALEXANDER JOO |
| Plan Check Approved | 10/6/2025 | ALEXANDER JOO |
| Issued | 12/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/10/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/10/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/4/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/18/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 8/18/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erusu,, Praneet Reddy; Lic. No.: C87773 | 6333 CANOGA AVENUE APT 266 WOODLAND HILLS, CA 91367 |
| Engineer | Mirhosseini,, Maj; Lic. No.: C60576 | 430 SANTIAGO AVE. LONG BEACH, CA 90814 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/16/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 1/16/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/21/2026 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 1/21/2026 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Conditional Approval | KIRK SANDERS |
| Pre-Inspection | 1/27/2026 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/11/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 2/11/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 2/11/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/23/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/23/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 2/23/2026 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/3/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 3/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 3/3/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/11/2026 | Approved | CHRISTOPHER ROJAS |
| Sewer | 3/11/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Wood Frame | 3/11/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 3/17/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/6/2026 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 4/6/2026 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 4/6/2026 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 4/10/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 4/10/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/30/2026 | Conditional Approval | JOSE AVILA |
| Drywall Nailing | 4/30/2026 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 4/30/2026 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/21/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Shower Pan | 5/21/2026 | Approved | KEVIN BERBERYAN |
| Shower Pan | 5/26/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/29/2026 | Approved | CHRISTOPHER ROJAS |