13712 W WEDDINGTON ST 91401

Certificate Information: 13712 W WEDDINGTON ST 91401

Application / Permit
25010-20000-00575
Plan Check / Job No.
B25VN03259
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g); EQUIPPED WITH NFPA 13-R FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
Issued on 3/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/7/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 SELLA BENYAMIN
Corrections Issued 2/18/2025 SELLA BENYAMIN
Quality Review Completed 2/18/2025 STEVEN KIM
Building Plans Picked Up 2/18/2025 APPLICANT
Plan Check Approved 3/25/2025 SELLA BENYAMIN
Issued 3/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/4/2025 LEE GUILBEAUX
Sewer availability Cleared 3/4/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/4/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/5/2025 LEE GUILBEAUX
Low Impact Development (LID) Cleared 3/19/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/19/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/1/2025 Approved RYAN SALAZAR
PLUMBING-Rough 5/1/2025 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 5/5/2025 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 5/8/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Partial Approval RYAN SALAZAR
HVAC-Rough 7/7/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 7/21/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Approved RYAN SALAZAR
PLUMBING-Rough 7/21/2025 Conditional Approval RYAN SALAZAR
Wood Frame 7/21/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/7/2025 Partial Approval RYAN SALAZAR
Shower Pan 8/13/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/20/2025 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/21/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/30/2025 Approved RYAN SALAZAR
Green Building Rough 9/30/2025 Approved RYAN SALAZAR
Insulation 9/30/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/30/2025 Approved RYAN SALAZAR
Drywall Nailing 10/8/2025 Approved WAYNE REGESTER