6336 N MURIETTA AVE 91401

Certificate Information: 6336 N MURIETTA AVE 91401

Application / Permit
25010-20000-00547
Plan Check / Job No.
B25VN03063
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan* New detached ADU per GC 66323(a)(2)
Permit Issued
Issued on 4/21/2025
Issuing Office
Current Status
CofO Issued on 5/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 MATTHEW TORRES
Corrections Issued 2/19/2025 MATTHEW TORRES
Quality Review Completed 2/20/2025 GARO TELMI
Applicant returned to address corrections 3/26/2025 MATTHEW TORRES
Plan Check Approved 4/17/2025 MATTHEW TORRES
Issued 4/21/2025 APPLICANT
CofO in Progress 2/16/2026 VINCENT HANLEY
Permit Finaled 5/5/2026 RUBEN SALAS
CofO Issued 5/5/2026 RUBEN SALAS
Permit Finaled 5/5/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/8/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/8/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 4/7/2025 ENRIQUE ACOSTA

Contact Information

Contractor Adu Building Company; Lic. No.: 1098802-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/6/2025 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/13/2025 Approved RYAN SALAZAR
Footing/Foundation/Slab 5/13/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 6/27/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 6/27/2025 Corrections Issued RYAN SALAZAR
Green Building Rough 6/27/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/27/2025 Partial Approval RYAN SALAZAR
Rough-Elec/Plmb/HVAC 6/27/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 6/27/2025 Approved RYAN SALAZAR
Wood Frame 6/27/2025 Approved RYAN SALAZAR
Insulation 7/3/2025 Approved RYAN SALAZAR
Drywall Nailing 7/14/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/28/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Sewer 7/28/2025 Approved GAREN HAYRAPETYAN
Shower Pan 7/28/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 7/28/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/31/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 12/18/2025 Approved RYAN SALAZAR
Final 12/18/2025 Corrections Issued RYAN SALAZAR
HVAC-Final 12/18/2025 Approved RYAN SALAZAR
PLUMBING-Final 12/18/2025 Approved RYAN SALAZAR
Final 2/13/2026 OK to Issue CofO VINCENT HANLEY
Green Building Final 2/13/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Not Required VINCENT HANLEY
Service/Power Release 2/13/2026 Approved VINCENT HANLEY
Smoke Detectors 2/13/2026 Approved VINCENT HANLEY