770 N ILIFF ST 90272
Certificate Information: 770 N ILIFF ST 90272
- Application / Permit
- 25010-20000-00520
- Plan Check / Job No.
- B25VN02893
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, BASEMENT (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Current Status
- Issued on 8/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | RARES BODEA |
| Corrections Issued | 2/7/2025 | RARES BODEA |
| Quality Review Completed | 2/11/2025 | STEVEN KIM |
| Building Plans Picked Up | 2/12/2025 | APPLICANT |
| Plan Check Approved | 8/18/2025 | RARES BODEA |
| Issued | 8/18/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/20/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 3/31/2025 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 5/28/2025 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/29/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Rough | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 8/26/2025 | Partial Inspection | KENNETH NAGLE |
| Pre-Inspection | 10/17/2025 | Partial Inspection | KENNETH NAGLE |
| Pre-Inspection | 10/28/2025 | Partial Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/31/2025 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 11/3/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/12/2025 | Partial Approval | STEPHANIE SWANSON |
| Masonry Wall/Backfill | 11/12/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/15/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 1/16/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | DANIEL VERA |
| Deputy Wood Construction | 3/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 5/21/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 6/4/2026 | Not Ready for Inspection | EVAN COOPER |