20512 W LULL ST 91306
Certificate Information: 20512 W LULL ST 91306
- Application / Permit
- 25010-20000-00479
- Plan Check / Job No.
- B25VN02686
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan (N) 2-STORY ADU. DETACHED ADU PER GC 66323(a)(2).
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Current Status
- Issued on 7/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | ADRIANA LOPEZ |
| Corrections Issued | 3/13/2025 | ADRIANA LOPEZ |
| Quality Review Completed | 3/20/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 5/28/2025 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 6/18/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 7/2/2025 | ADRIANA LOPEZ |
| Issued | 7/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/22/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/27/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/2/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/6/2025 | Partial Approval | ALEXANDER HANDY |
| Pre-Inspection | 8/6/2025 | Partial Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 8/12/2025 | Corrections Issued | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 8/18/2025 | Approved | SCOTT SOBEL |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 9/3/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 9/3/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Deputy Wood Construction | 9/17/2025 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 9/19/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 9/19/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 9/19/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/6/2025 | Approved | TROY SANDERS |
| HVAC-Rough | 11/6/2025 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 11/6/2025 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 11/6/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 11/20/2025 | Conditional Approval | ALEXANDER HANDY |
| Green Building Rough | 11/20/2025 | Approved | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 11/20/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 11/20/2025 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 11/20/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/15/2025 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 12/22/2025 | Approved | TROY SANDERS |
| Sewer | 12/22/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 1/8/2026 | Approved | KRISTEN CAUSEY |
| Shower Pan | 3/13/2026 | Approved | DAVID FASTIGGI |
| Interior/Exterior Lathing | 3/18/2026 | Partial Approval | ALEXANDER HANDY |