8810 N ODESSA AVE 91343
Certificate Information: 8810 N ODESSA AVE 91343
- Application / Permit
- 25010-20000-00470
- Plan Check / Job No.
- B25VN02636
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan new detached ADU per ordinance
- Permit Issued
- Issued on 4/9/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | LUKE GONZALES |
| Corrections Issued | 2/7/2025 | LUKE GONZALES |
| Applicant returned to address corrections | 3/26/2025 | SUNMIN LEE |
| Plan Check Approved | 4/2/2025 | SUNMIN LEE |
| Issued | 4/9/2025 | APPLICANT |
| CofO in Progress | 9/11/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
| CofO Issued | 9/23/2025 | RUBEN SALAS |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 3/18/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 3/18/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/19/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Akf Construction Inc; Lic. No.: 1086127-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/20/2025 | Partial Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 5/28/2025 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Wood Frame | 6/20/2025 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 6/30/2025 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 7/8/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/8/2025 | Approved | SALVADOR MARTINEZ |
| Sewer | 7/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 7/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 7/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Sewer | 7/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 7/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 7/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 7/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 7/18/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 7/21/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 7/25/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 7/25/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 7/28/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 7/28/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 8/6/2025 | Approved | LOUIS ESCOTO |
| Underground Mechanical | 8/11/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 9/8/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 9/8/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 9/8/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Service/Power Release | 9/8/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 9/8/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 9/11/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 9/11/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 9/11/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 9/11/2025 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 9/11/2025 | Approved | GAREN HAYRAPETYAN |